1426 W 253RD ST 90710

Certificate Information: 1426 W 253RD ST 90710

Application / Permit
24010-10000-02726
Plan Check / Job No.
B24LA12501
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 8/21/2024
Issuing Office
Current Status
CofO Issued on 5/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2024 APPLICANT
Assigned to Plan Check Engineer 7/5/2024 SARKIS HARABEDIAN
Corrections Issued 7/8/2024 SARKIS HARABEDIAN
Applicant returned to address corrections 7/31/2024 GURUNATH NESARAJAH
Plan Check Approved 8/18/2024 GURUNATH NESARAJAH
Issued 8/21/2024 APPLICANT
CofO in Progress 5/2/2025 EUGENE CASSIDY
Permit Finaled 5/2/2025 ANSON MAGLASANG
CofO Issued 5/2/2025 ANSON MAGLASANG
Permit Finaled 5/2/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/18/2024 ERIK BEASLEY
"Q" conditions Cleared 7/23/2024 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 7/29/2024 ERIK BEASLEY
Sewer availability Cleared 7/29/2024 ERIK BEASLEY

Contact Information

Contractor The Adu Guys Com Inc; Lic. No.: 1071442-B       ,
Contractor The Adu Guys.Com Inc; Lic. No.: 1071442-B       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/5/2024 Approved JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 9/5/2024 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 9/5/2024 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 9/5/2024 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 9/13/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 9/19/2024 Corrections Issued JOSEPH MCGARRY
METHANE-Rough 9/19/2024 Approved JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 9/19/2024 Corrections Issued JOSEPH MCGARRY
BUILDING-Rough-Frame 10/3/2024 Corrections Issued EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 10/3/2024 Partial Approval EUGENE CASSIDY
Deputy Drilled-In Anchors 10/4/2024 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Partial Approval EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 10/7/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/10/2024 Approved EUGENE CASSIDY
Insulation 10/10/2024 Approved EUGENE CASSIDY
Drywall Nailing 10/16/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/16/2024 Partial Approval EUGENE CASSIDY
Underground Mechanical 11/5/2024 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 12/12/2024 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/17/2025 SGSOV Not Ready EUGENE CASSIDY
Final 4/21/2025 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/21/2025 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 4/21/2025 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 5/1/2025 Approved EUGENE CASSIDY
Final 5/1/2025 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 5/1/2025 Approved EUGENE CASSIDY
PLUMBING-Final 5/1/2025 Approved EUGENE CASSIDY
Smoke Detectors 5/1/2025 Approved EUGENE CASSIDY