16403 W GILMORE ST 91406
Certificate Information: 16403 W GILMORE ST 91406
- Application / Permit
- 24010-10000-02725
- Plan Check / Job No.
- B24LA12490
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 11/15/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 7/23/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 7/25/2024 | KEN GILL |
| Building Plans Picked Up | 8/9/2024 | APPLICANT |
| Plan Check Approved | 11/14/2024 | MAHNAZ NOURHASHEMI |
| Issued | 11/15/2024 | APPLICANT |
| CofO in Progress | 9/30/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 10/3/2025 | RUBEN SALAS |
| CofO Issued | 10/3/2025 | RUBEN SALAS |
| Permit Finaled | 10/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/24/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 7/24/2024 | BIAINA HARITUNIAN |
| ZI | Cleared | 7/30/2024 | JAZMIN ROQUE |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/8/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 10/20/2024 | TINA MIRANDA |
| Construction within easement | Cleared | 10/20/2024 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pinzon,, Eduardo Andres; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/19/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 12/19/2024 | Partial Approval | RAUL OLAGI |
| Sewer | 12/19/2024 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 12/30/2024 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| PLUMBING-Rough | 3/6/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 3/10/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2025 | Partial Approval | SALVADOR MARTINEZ |
| PLUMBING-Rough | 3/11/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 3/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 3/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 4/2/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 4/2/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 4/7/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 4/7/2025 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 4/7/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 4/11/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 4/11/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 4/11/2025 | Partial Approval | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 4/11/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/14/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 4/17/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Insulation | 4/21/2025 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 4/24/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 5/8/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 5/9/2025 | Approved | GAREN HAYRAPETYAN |
| Underground Mechanical | 6/5/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 6/10/2025 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Final | 8/1/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 8/1/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 8/1/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Final | 8/1/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 8/1/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 8/1/2025 | SGSOV No Gas | SALVADOR MARTINEZ |
| Service/Power Release | 8/1/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 8/1/2025 | Approved | SALVADOR MARTINEZ |
| Final | 8/18/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 8/18/2025 | Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 8/18/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Final | 9/25/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 9/25/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 9/30/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Service/Power Release | 9/30/2025 | Approved | GAREN HAYRAPETYAN |