1366 W 37TH DR 90007

Certificate Information: 1366 W 37TH DR 90007

Application / Permit
24010-10000-02700
Plan Check / Job No.
B24LA12359
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
New 1-story commercial building for parking lot. (EV CHARGERS, FENCE, CANOPIES AND SITE WALLS UNDER SEPARATE PERMITS)
Permit Issued
Issued on 6/18/2025
Issuing Office
Current Status
Issued on 6/18/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/1/2024 APPLICANT
Assigned to Plan Check Engineer 7/3/2024 JOE VO
Corrections Issued 7/6/2024 JOE VO
Quality Review Completed 7/8/2024 GARO TELMI
Assigned to Zoning Architect 7/11/2024 CALEB WONG
Applicant returned to address corrections 10/29/2024 JOE VO
Applicant returned to address corrections 5/20/2025 JOE VO
Plan Check Approved 6/18/2025 JOE VO
Issued 6/18/2025 APPLICANT

Permit Application Clearance Information

CPC Cleared 7/25/2024 MATHEW QUAN
Miscellaneous Cleared 7/25/2024 MATHEW QUAN
Miscellaneous Cleared 7/25/2024 MATHEW QUAN
Miscellaneous Cleared 7/25/2024 MATHEW QUAN
Miscellaneous Cleared 7/25/2024 MATHEW QUAN
Miscellaneous Cleared 7/25/2024 MATHEW QUAN
ZA Case Cleared 7/25/2024 MATHEW QUAN
ZA Case Cleared 7/25/2024 MATHEW QUAN
ZA Case Cleared 7/25/2024 MATHEW QUAN
"D" conditions Cleared 7/29/2024 MATHEW QUAN
Eng Process Fee Ord 176,300 Cleared 8/13/2024 CELINA MORENO
Metro Rail approval Cleared 10/10/2024 JENNIFER SU
Highway dedication Cleared 11/13/2024 TREVOR QUAN
Community Plan Implem. Overlay Cleared 1/29/2025 MANERI ROMAN
Address approval Cleared 3/11/2025 WALLIE JONG
Community Plan Implem. Overlay Cleared 3/11/2025 WALLIE JONG
Sewer availability Cleared 3/11/2025 WALLIE JONG
Permit Cleared 3/12/2025 ADRIAN SANCHEZ
Low Impact Development (LID) Cleared 3/14/2025 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 3/21/2025 JEANIE LAM
Community Plan Implem. Overlay Cleared 4/2/2025 JOSE CARDENAS
Community Plan Implem. Overlay Cleared 4/7/2025 RIDWAN HARDY
Community Plan Implem. Overlay Cleared 4/11/2025 BRANDON WONG
Prkng lot landscape/Water mgmt Cleared 4/17/2025 FIPE LEILUA
DAS Clearance Cleared 4/24/2025 Joseph Rafols
Green Code Cleared 5/24/2025 Joseph Rafols
Zoning Plan Check Cleared 6/10/2025 Joseph Rafols

Contact Information

Contractor Smith And Severson Builders Llc; Lic. No.: 989943-B       ,
Engineer Gerges,, Rafik; Lic. No.: S5092 301 N LAKE AVE.   SUITE 500    PASADENA, CA 91101

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/2/2025 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 9/9/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Not Ready for Inspection JAMES POWERS
Wood Frame 10/3/2025 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Not Ready for Inspection JAMES POWERS
Wood Frame 10/6/2025 Not Ready for Inspection JAMES POWERS
Wood Frame 10/27/2025 Partial Approval JAMES POWERS
Insulation 11/19/2025 Not Ready for Inspection JAMES POWERS
Insulation 12/1/2025 Partial Approval JAMES POWERS
Drywall Nailing 12/9/2025 Approved JAMES POWERS
Footing/Foundation/Slab 1/23/2026 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/2/2026 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/11/2026 Partial Approval JAMES POWERS