14683 W BASHFORD ST 90272

Certificate Information: 14683 W BASHFORD ST 90272

Application / Permit
24010-10000-02689
Plan Check / Job No.
B24LA12279
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: CONSTRUCT (N) DETACHED 2-STORY ACCESSORY BUILDING WITH GARAGE (416SQFT) AND OFFICE (220SQFT) ON FIRST FLOOR AND ADU (712SQFT) ON SECOND FLOOR PER ORDINACE ***SPRINKLER 13D REQUIRED***
Permit Issued
Issued on 12/10/2024
Issuing Office
Current Status
Issued on 12/10/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/1/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 KHUONG TRUONG
Corrections Issued 7/25/2024 KHUONG TRUONG
Quality Review Completed 7/25/2024 GARO TELMI
Applicant returned to address corrections 8/20/2024 KHUONG TRUONG
Applicant returned to address corrections 9/18/2024 KHUONG TRUONG
Plan Check Approved 12/9/2024 KHUONG TRUONG
Issued 12/10/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/13/2024 DINAH GARIN
Roof/Waste drainage to street Cleared 8/13/2024 DINAH GARIN
Construction near power lines Cleared 8/19/2024 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 8/19/2024 DINAH GARIN
Sewer availability Cleared 8/19/2024 DINAH GARIN
Permit Cleared 11/20/2024 HISASHI KOBAYAKAWA
Trees in Parkway Cleared 11/20/2024 ADALBERTO VERA
Hydrant and Access approval Cleared 12/3/2024 PATRICK PEREZ

Contact Information

Architect Frank,, Joshua; Lic. No.: NA34411       ,
Contractor Harman Kenyon Construction Inc; Lic. No.: 852631-B       ,
Engineer Franceschi,, Paul; Lic. No.: NA4309       ,
Engineer Franceschi,, Paul; Lic. No.: S4309 2388 KENILWORTH AVE      LOS ANGELES, CA 90039
Engineer Mirzadeh,, Amir; Lic. No.: C58119 P O BOX 572110      TARZANA, CA 91357

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/12/2026 Partial Inspection TEMISTOCLES CAAL
Pre-Inspection 3/24/2026 Partial Inspection TEMISTOCLES CAAL
Sewer 3/27/2026 Approved MICHAEL ALLEN
Sewer 4/6/2026 Approved MICHAEL ALLEN
Underground Mechanical 4/6/2026 Approved MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 4/15/2026 Approved TEMISTOCLES CAAL
Footing/Foundation/Slab 4/15/2026 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 5/4/2026 Partial Approval TEMISTOCLES CAAL
Deputy Wood Construction 5/11/2026 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 5/27/2026 Approved JESUS PINEDA