4600 N GREENBUSH AVE 91423

Certificate Information: 4600 N GREENBUSH AVE 91423

Application / Permit
24010-10000-02608
Plan Check / Job No.
B24LA11896
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 31'-0" x 18'-0" DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g). ***"COMPLY WITH DEPARTMENT ORDER effective date 04/05/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"****
Permit Issued
Issued on 12/27/2024
Issuing Office
Current Status
Issued on 12/27/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/21/2024 APPLICANT
Assigned to Plan Check Engineer 6/27/2024 SARKIS HARABEDIAN
Corrections Issued 6/28/2024 SARKIS HARABEDIAN
Plan Check Approved 11/26/2024 ISIS ARGUETA
Issued 12/27/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/3/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/3/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/6/2024 CARLOS AGUILERA
Sewer availability Cleared 8/6/2024 CARLOS AGUILERA
Construction near power lines Cleared 11/22/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/2/2025 Not Ready for Inspection JUAN VALENZUELA
Underground Mechanical 7/2/2025 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 7/14/2025 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 7/17/2025 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 7/24/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 8/27/2025 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/27/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 8/27/2025 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 9/5/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 9/5/2025 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/5/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 9/5/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 9/5/2025 Corrections Issued MISAEL ESPARZA
MERV13>=Rough 9/5/2025 Approved MISAEL ESPARZA
PLUMBING-Rough 9/5/2025 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 9/5/2025 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 9/17/2025 Approved Pending GreenApproval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/17/2025 Approved MISAEL ESPARZA
Green Building Rough 9/17/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 9/17/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 9/22/2025 Partial Approval MISAEL ESPARZA
Underground Mechanical 9/24/2025 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 9/29/2025 Approved MISAEL ESPARZA
Insulation 10/1/2025 No Access for Inspection MISAEL ESPARZA
Insulation 10/3/2025 Approved DAVID MATSON
Drywall Nailing 10/14/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 10/14/2025 Approved MICHAEL CORTEZ
Shower Pan 10/14/2025 Approved MICHAEL CORTEZ
Gas Test 11/6/2025 Partial Approval MISAEL ESPARZA
Underground Mechanical 12/17/2025 Partial Approval MISAEL ESPARZA