231 S KINGSLEY DR 90004

Certificate Information: 231 S KINGSLEY DR 90004

Application / Permit
24010-10000-02606
Plan Check / Job No.
B24LA11893
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY 25' X 29'-8" A.D.U. PER ENGINEER DESIGN (800 SF max New Construction per State Law, CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)) COMPLY WITH DEPARTMENT ORDER effective date 05/17/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 12/9/2024
Issuing Office
Metro
Current Status
CofO Issued on 9/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2024 APPLICANT
Assigned to Plan Check Engineer 6/25/2024 LAWRENCE QUIRANTE
Corrections Issued 6/25/2024 LAWRENCE QUIRANTE
Building Plans Picked Up 6/28/2024 APPLICANT
Applicant returned to address corrections 7/18/2024 AUNG SOE
Applicant returned to address corrections 10/31/2024 FERNANDO FLORES
Plan Check Approved 11/7/2024 JOSE VELAZQUEZ
Issued 12/9/2024 APPLICANT
CofO in Progress 9/17/2025 WILLIAM MICHALAK
Permit Finaled 9/29/2025 CLAUDIO MORENO
CofO Issued 9/29/2025 CLAUDIO MORENO
Permit Finaled 9/29/2025 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 6/27/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 6/27/2024 DAVID VO
Roof/Waste drainage to street Cleared 6/27/2024 CHRISTINA BRACO
Sewer availability Cleared 6/27/2024 DAVID VO
Construction near power lines Cleared 10/30/2024 TINA MIRANDA

Contact Information

Contractor Mcinc Construction Inc; Lic. No.: 1087192-B 12002 PAINTER AVE      WHITTIER, CA 90605
Engineer Pinzon,, Eduardo Andres; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/12/2024 Corrections Issued WILLIAM MICHALAK
METHANE-Barrier 12/12/2024 Approved WILLIAM MICHALAK
METHANE-Subgrade 12/12/2024 Approved WILLIAM MICHALAK
Underground Mechanical 1/6/2025 Approved WILLIAM MICHALAK
Wood Frame 1/6/2025 Partial Approval WILLIAM MICHALAK
Drywall Nailing 1/13/2025 Not Ready for Inspection WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Partial Approval WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Approved LUIS CORRAL
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 2/10/2025 Not Ready for Inspection WILLIAM MICHALAK
ELECTRICAL-Rough 2/10/2025 Corrections Issued WILLIAM MICHALAK
Green Building Rough 2/10/2025 Corrections Issued WILLIAM MICHALAK
HVAC-Rough 2/10/2025 Corrections Issued WILLIAM MICHALAK
Interior/Exterior Lathing 2/10/2025 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Rough 2/10/2025 Approved WILLIAM MICHALAK
PLUMBING-Rough 2/10/2025 Partial Approval WILLIAM MICHALAK
Verify Sprinkler Sign Off 2/10/2025 Not Ready for Inspection WILLIAM MICHALAK
Insulation 2/14/2025 Approved WILLIAM MICHALAK
Drywall Nailing 2/19/2025 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 6/24/2025 Approved WILLIAM MICHALAK
ELECTRICAL-Final 6/24/2025 Not Ready for Inspection WILLIAM MICHALAK
Final 6/24/2025 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 6/24/2025 Approved WILLIAM MICHALAK
Green Building Final 6/24/2025 Approved WILLIAM MICHALAK
Green Building Rough 6/24/2025 Approved WILLIAM MICHALAK
HVAC-Final 6/24/2025 Not Ready for Inspection WILLIAM MICHALAK
PLUMBING-Final 6/24/2025 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 6/24/2025 SGSOV Not Ready WILLIAM MICHALAK
Service/Power Release 6/24/2025 Conditional Approval WILLIAM MICHALAK
Smoke Detectors 6/24/2025 Approved WILLIAM MICHALAK
Verify Sprinkler Sign Off 6/24/2025 Approved WILLIAM MICHALAK
ELECTRICAL-Final 7/18/2025 Approved WILLIAM MICHALAK
Final 7/18/2025 Not Ready for Inspection WILLIAM MICHALAK
Gas Test 7/18/2025 Not Ready for Inspection WILLIAM MICHALAK
HVAC-Final 7/18/2025 Approved WILLIAM MICHALAK
PLUMBING-Final 7/18/2025 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 7/18/2025 SGSOV Approved WILLIAM MICHALAK
Service/Power Release 7/18/2025 Not Ready for Inspection WILLIAM MICHALAK
ELECTRICAL-Final 7/22/2025 Approved WILLIAM MICHALAK
Final 7/22/2025 OK to Issue CofO WILLIAM MICHALAK
HVAC-Final 7/22/2025 Approved WILLIAM MICHALAK
PLUMBING-Final 7/22/2025 Approved WILLIAM MICHALAK
Service/Power Release 7/22/2025 Approved WILLIAM MICHALAK