4510 N ATOLL AVE 91423
Certificate Information: 4510 N ATOLL AVE 91423
- Application / Permit
- 24010-10000-02574
- Plan Check / Job No.
- B24LA11652
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan - NEW 2 STORY ADU PER 12.22 A33 C & D
- Permit Issued
- Issued on 3/17/2025
- Issuing Office
- Current Status
- Issued on 3/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/5/2024 | STARR CHEN |
| Corrections Issued | 7/11/2024 | STARR CHEN |
| Quality Review Completed | 7/15/2024 | EUGENE BARBEAU |
| Applicant returned to address corrections | 9/27/2024 | STARR CHEN |
| Applicant returned to address corrections | 12/12/2024 | STARR CHEN |
| Plan Check Approved | 2/6/2025 | STARR CHEN |
| Issued | 3/17/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/10/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/10/2024 | RIDWAN HARDY |
| Address approval | Cleared | 10/16/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 10/16/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 10/17/2024 | RYAN CASTRO |
| ZI | Cleared | 10/22/2024 | ASHLEY RODARTE |
| Hydrant and Access approval | Cleared | 1/6/2025 | JERRY KAO |
Contact Information
| Architect | Nassirpour,, Babak; Lic. No.: NA26861 | , |
| Contractor | Lannen Construction Inc; Lic. No.: 811038-B | 1545 SAWTELLE BLVD STE 22 LOS ANGELES, CA 90025 |
| Engineer | Liu,, Wen-Young; Lic. No.: C70729 | 448 LINWOOD AVE MONROVIA, CA 91016 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/15/2025 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 4/22/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 4/24/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 4/25/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 5/1/2025 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 5/13/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 5/21/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 5/21/2025 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 5/22/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 5/22/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/2/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 6/5/2025 | Corrections Issued | JACK KARGODORIAN |
| Insulation | 6/9/2025 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 6/12/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 7/2/2025 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 7/2/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 7/25/2025 | Approved | LOUIS ESCOTO |
| Underground Mechanical | 10/6/2025 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 10/24/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 10/24/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 10/24/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 10/24/2025 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 10/24/2025 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 10/24/2025 | Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 10/24/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 11/14/2025 | Conditional Approval | CHRISTOPHE COCHRAN |
| Green Building Final | 11/14/2025 | Approved | CHRISTOPHE COCHRAN |