Eplan. New 1-Story SFD per SB9 under Two Unit Development -Bldg Sprinklered Thru-out
Permit Issued
Issued on 10/7/2024
Issuing Office
Current Status
CofO Issued on 1/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2024 APPLICANT
Assigned to Plan Check Engineer 6/19/2024 MAHNAZ NOURHASHEMI
Corrections Issued 6/26/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 7/1/2024 TU HUA
Plan Check Approved 9/23/2024 MAHNAZ NOURHASHEMI
Issued 10/7/2024 APPLICANT
CofO in Progress 9/2/2025 ARUTYUN MADATYAN
Permit Finaled 1/30/2026 JOHN JANSON
CofO Issued 1/30/2026 JOHN JANSON
Permit Finaled 1/30/2026 JOHN JANSON

Permit Application Clearance Information

Senate Bill 9 Cleared 7/3/2024 ASHLEY RODARTE
ZA Case Cleared 7/3/2024 ASHLEY RODARTE
Address approval Cleared 7/13/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/13/2024 CARLOS AGUILERA
Sewer availability Cleared 7/13/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/15/2024 CARLOS AGUILERA
Hydrant and Access approval Cleared 9/9/2024 RUEL COLE

Contact Information

Contractor Owner-Builder       ,
Engineer Chatsky,, German; Lic. No.: C84153 3876 HUNTERS GROVE CT      MOORPARK, CA 93021

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/18/2024 Partial Inspection HENRY KIM
Footing/Foundation/Slab 2/25/2025 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 2/25/2025 Partial Approval HENRY KIM
Footing/Foundation/Slab 3/4/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 3/13/2025 Corrections Issued ARUTYUN MADATYAN
ELECTRICAL-Rough 3/27/2025 Approved ARUTYUN MADATYAN
HVAC-Rough 3/27/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 3/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 3/27/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 4/2/2025 Partial Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 4/9/2025 Conditional Approval ARUTYUN MADATYAN
Green Building Rough 4/9/2025 Approved ARUTYUN MADATYAN
Shower Pan 4/9/2025 Approved ARUTYUN MADATYAN
Verify Sprinkler Sign Off 4/9/2025 Approved ARUTYUN MADATYAN
Insulation 4/21/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 4/23/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 4/29/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 5/30/2025 Partial Approval ARUTYUN MADATYAN
Sewer 5/30/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 6/26/2025 Approved JUAN ALVARADO
ELECTRICAL-Final 6/26/2025 Approved JUAN ALVARADO
Final 6/26/2025 Corrections Issued JUAN ALVARADO
HVAC-Final 6/26/2025 Partial Approval JUAN ALVARADO
PLUMBING-Final 6/26/2025 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 6/26/2025 SGSOV Not Required JUAN ALVARADO
Service/Power Release 6/26/2025 Not Ready for Inspection JUAN ALVARADO
Smoke Detectors 6/26/2025 Approved JUAN ALVARADO
Final 7/16/2025 Not Ready for Inspection ARUTYUN MADATYAN
Service/Power Release 7/16/2025 Not Ready for Inspection ARUTYUN MADATYAN
Final 9/2/2025 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 9/2/2025 Approved ARUTYUN MADATYAN
Service/Power Release 9/2/2025 Approved ARUTYUN MADATYAN