1508 N OLD OAK ROAD 90049
Certificate Information: 1508 N OLD OAK ROAD 90049
- Application / Permit
- 24010-10000-02514
- Plan Check / Job No.
- B24LA11297
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- [ePlan] NEW DETACHED 1-STORY ACCESSORY LIVING QUARTERS
- Permit Issued
- Issued on 7/22/2025
- Issuing Office
- Current Status
- Issued on 7/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 6/25/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 6/25/2024 | GARO TELMI |
| Plan Check Approved | 1/14/2025 | ARSALAN SHABESTARI |
| Issued | 7/22/2025 | APPLICANT |
Permit Application Clearance Information
| Tract Map conditions | Cleared | 8/9/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 8/9/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 8/9/2024 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2024 | DARIN LAM |
| Sewer availability | Cleared | 8/12/2024 | DARIN LAM |
| Low Impact Development (LID) | Cleared | 8/13/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/20/2024 | DARIN LAM |
| Miscellaneous | Cleared | 8/23/2024 | ANNA VIDAL |
| Hydrant and Access approval | Cleared | 11/18/2024 | RUEL COLE |
| GPI Written Notices | Cleared | 1/14/2025 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 1/14/2025 | ARSALAN SHABESTARI |
Contact Information
| Architect | Salice,, Alexandre; Lic. No.: NA35383 | , |
| Contractor | Kor Design Build; Lic. No.: 1026877-B | , |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/1/2025 | Partial Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/26/2025 | Conditional Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 10/28/2025 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/24/2025 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 11/26/2025 | Approved | KEVIN SARGSYAN |
| Gas Test | 1/29/2026 | Corrections Issued | KEVIN SARGSYAN |
| Underground Mechanical | 1/29/2026 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 2/2/2026 | Conditional Approval | JUAN VALENZUELA |
| Underground Mechanical | 2/3/2026 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2026 | Partial Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/24/2026 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 3/5/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/5/2026 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 3/16/2026 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 3/19/2026 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/19/2026 | Approved | KEVIN SARGSYAN |
| Insulation | 4/3/2026 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 4/8/2026 | Approved | HERBERT GIRON |
| Insulation | 4/8/2026 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/15/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 4/15/2026 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 4/21/2026 | Approved | KEVIN SARGSYAN |
| Shower Pan | 4/22/2026 | Approved | KEVIN SARGSYAN |
| Insulation | 4/24/2026 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 5/1/2026 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 5/1/2026 | Corrections Issued | MICHAEL ALLEN |
| Interior/Exterior Lathing | 5/4/2026 | Approved | KEVIN SARGSYAN |