10919 S ANZAC AVE 90059

Certificate Information: 10919 S ANZAC AVE 90059

Application / Permit
24010-10000-02493
Plan Check / Job No.
B24LA11222
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD
Permit Issued
Issued on 3/27/2025
Issuing Office
Metro
Current Status
Issued on 3/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/12/2024 APPLICANT
Assigned to Plan Check Engineer 6/13/2024 ARSALAN SHABESTARI
Corrections Issued 6/18/2024 ARSALAN SHABESTARI
Quality Review Completed 6/28/2024 KEN GILL
Building Plans Picked Up 7/9/2024 APPLICANT
Plan Check Approved 3/13/2025 ARSALAN SHABESTARI
Issued 3/27/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/8/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 10/8/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/9/2024 WALLIE JONG
Sewer availability Cleared 12/2/2024 DAVID LOPEZ
Hydrant and Access approval Cleared 1/14/2025 JOHN CONNEALLY

Contact Information

Contractor Ebenezer Construction; Lic. No.: 657529-B 9214 MANZANAR AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/3/2025 Partial Approval ANTHONY EGSON
PLUMBING-Rough 4/3/2025 Not Ready for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 5/27/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 5/27/2025 Approved ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 5/29/2025 Partial Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/27/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/8/2025 Partial Approval ANTHONY EGSON
PLUMBING-Rough 9/8/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 9/11/2025 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Approved ANTHONY EGSON
Verify Sprinkler Sign Off 9/11/2025 Approved ANTHONY EGSON
Green Building Rough 9/16/2025 Approved ANTHONY EGSON
HVAC-Rough 9/16/2025 Approved ANTHONY EGSON
Insulation 10/9/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 10/9/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 11/3/2025 Approved ANTHONY EGSON
Drywall Nailing 11/3/2025 Approved ANTHONY EGSON
Sewer 2/4/2026 Approved ARTHUR NEGRETE
ELECTRICAL-Final 3/5/2026 Approved ARTHUR NEGRETE
Final 3/5/2026 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 3/5/2026 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Final 3/5/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 3/5/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 3/5/2026 SGSOV Not Ready ARTHUR NEGRETE
Service/Power Release 3/5/2026 Not Ready for Inspection ARTHUR NEGRETE
Smoke Detectors 3/5/2026 Approved ARTHUR NEGRETE
ELECTRICAL-Final 3/16/2026 Approved ARTHUR NEGRETE
Final 3/16/2026 Partial Approval ARTHUR NEGRETE
Green Building Final 3/16/2026 Approved ARTHUR NEGRETE
HVAC-Final 3/16/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 3/16/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 3/16/2026 SGSOV Not Required ARTHUR NEGRETE
Service/Power Release 3/16/2026 Approved ARTHUR NEGRETE