4211 N ELMER AVE 91602

Certificate Information: 4211 N ELMER AVE 91602

Application / Permit
24010-10000-02470
Plan Check / Job No.
B24LA11117
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g); NFPA13-D FIRE SPRINKLERE THROUGHOUT BUILDING
Permit Issued
Issued on 10/2/2024
Issuing Office
Current Status
CofO Issued on 5/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2024 APPLICANT
Assigned to Plan Check Engineer 6/13/2024 SINA KHOSRAVI
Corrections Issued 6/18/2024 SINA KHOSRAVI
Quality Review Completed 6/20/2024 KEN GILL
Building Plans Picked Up 6/25/2024 APPLICANT
Applicant returned to address corrections 8/21/2024 SINA KHOSRAVI
Plan Check Approved 9/18/2024 SINA KHOSRAVI
Issued 10/2/2024 APPLICANT
CofO in Progress 5/4/2026 JAVIER RAMOS JR
Permit Finaled 5/19/2026 RUBEN SALAS
CofO Issued 5/19/2026 RUBEN SALAS
Permit Finaled 5/19/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/25/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/25/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/26/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/26/2024 BIAINA HARITUNIAN
ZI Cleared 8/9/2024 DORIAN AGUILAR
Construction near power lines Cleared 8/23/2024 RIDWAN HARDY

Contact Information

Architect Schneider,, Brent T; Lic. No.: C21821 3350 WILLOW LANE      WESTLAKE VILLAGE, CA 91361
Contractor Jd Emory, Inc; Lic. No.: 1126884-B 16133 VENTURA BOULEVARD   STE 700    ENCINO, CA 91436

Inspector Information

DANIEL ORRANTE, (818) 374-1157 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/18/2024 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 10/18/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/4/2024 Partial Inspection CHRISTOPHER ROJAS
Green Building Rough 12/4/2024 Partial Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 12/4/2024 Partial Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/11/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 12/11/2024 Partial Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 12/11/2024 Partial Inspection CHRISTOPHER ROJAS
Wood Frame 12/24/2024 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 3/21/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 5/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Shower Pan 5/5/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
HVAC-Rough 6/4/2025 Partial Inspection JAVIER RAMOS JR
Underground Mechanical 6/4/2025 Partial Approval JAVIER RAMOS JR
Insulation 6/12/2025 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 6/12/2025 Not Ready for Inspection MISAEL ESPARZA
Insulation 6/18/2025 Partial Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 6/18/2025 Partial Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 6/23/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 7/1/2025 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 7/1/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/7/2025 Partial Approval JAVIER RAMOS JR
Insulation 7/7/2025 Approved JAVIER RAMOS JR
Drywall Nailing 7/15/2025 Partial Approval JAVIER RAMOS JR
HVAC-Rough 7/15/2025 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 9/22/2025 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 9/22/2025 Partial Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 10/27/2025 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 5/4/2026 Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/4/2026 Approved JAVIER RAMOS JR
Final 5/4/2026 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 5/4/2026 Approved JAVIER RAMOS JR
Green Building Rough 5/4/2026 Approved JAVIER RAMOS JR
HVAC-Final 5/4/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 5/4/2026 Approved JAVIER RAMOS JR
Service/Power Release 5/4/2026 Approved JAVIER RAMOS JR
Smoke Detectors 5/4/2026 Approved JAVIER RAMOS JR