18726 W COVELLO ST 91335
Certificate Information: 18726 W COVELLO ST 91335
- Application / Permit
- 24010-10000-02452
- Plan Check / Job No.
- B24LA10990
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU per LAMC 12.22 A.33 (c)(d) R3 occupacy
- Permit Issued
- Issued on 12/24/2024
- Issuing Office
- Metro
- Current Status
- CofO Corrected on 4/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2024 | KELVIN CHUONG |
| Corrections Issued | 6/10/2024 | KELVIN CHUONG |
| Building Plans Picked Up | 6/26/2024 | APPLICANT |
| Applicant returned to address corrections | 8/9/2024 | SUNMIN LEE |
| Plan Check Approved | 12/24/2024 | EDWIN MARTINEZ |
| Issued | 12/24/2024 | APPLICANT |
| CofO in Progress | 4/8/2026 | ARUTYUN MADATYAN |
| CofO Issued-Status Void | 4/13/2026 | JOHN JANSON |
| Permit Finaled-Status Void | 4/13/2026 | JOHN JANSON |
| Re-Activate Permit | 4/14/2026 | JOHN JANSON |
| Permit Finaled | 4/14/2026 | JOHN JANSON |
| CofO Corrected | 4/14/2026 | JOHN JANSON |
| Permit Finaled | 4/14/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/8/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/11/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 12/4/2024 | ENRIQUE ACOSTA |
| Disturb/Remove Protected Trees | Cleared | 12/23/2024 | RICHARD SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/21/2025 | Corrections Issued | ARUTYUN MADATYAN |
| PLUMBING-Rough | 1/21/2025 | Partial Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 2/24/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 5/21/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Corrections Issued | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/21/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 6/16/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 6/23/2025 | Partial Approval | ARUTYUN MADATYAN |
| Green Building Rough | 6/23/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 6/25/2025 | Conditional Approval | KRISTEN CAUSEY |
| Insulation | 6/30/2025 | Approved | GEVORK IPCHYAN |
| Drywall Nailing | 7/11/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 12/15/2025 | Conditional Approval | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 12/15/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 12/15/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 12/15/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 12/15/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 12/15/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 12/15/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 12/15/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 12/15/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 12/15/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 12/30/2025 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 3/19/2026 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 3/19/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 3/19/2026 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 3/19/2026 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 3/19/2026 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 3/19/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 3/19/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 4/7/2026 | Approved | ARUTYUN MADATYAN |
| Final | 4/7/2026 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 4/7/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 4/7/2026 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 4/7/2026 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 4/7/2026 | Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 4/7/2026 | Approved | ARUTYUN MADATYAN |