1356-1356 1/2 E 108TH ST 90059
Certificate Information: 1356-1356 1/2 E 108TH ST 90059
- Application / Permit
- 24010-10000-02442
- Plan Check / Job No.
- B24LA10930
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD WIDTH ATTACHED ADU PER LAMC 12.22 A.33 (c) and (e) AND ATTACHED 1-CAR GARAGE -BLDG SPRINKLERED THRU-OUT
- Permit Issued
- Issued on 6/24/2025
- Issuing Office
- Current Status
- CofO Issued on 4/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 6/21/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 6/21/2024 | KEN GILL |
| Building Plans Picked Up | 6/25/2024 | APPLICANT |
| Plan Check Approved | 5/28/2025 | MAHNAZ NOURHASHEMI |
| Issued | 6/24/2025 | APPLICANT |
| CofO in Progress | 4/8/2026 | ARTHUR NEGRETE |
| Permit Finaled | 4/8/2026 | ANSON MAGLASANG |
| CofO Issued | 4/8/2026 | ANSON MAGLASANG |
| Permit Finaled | 4/8/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2024 | JESSICA OPINION |
| Hydrant and Access approval | Cleared | 11/6/2024 | JERRY KAO |
| Roof/Waste drainage to street | Cleared | 4/16/2025 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2025 | JEANIE LAM |
| Sewer availability | Cleared | 5/8/2025 | JEANIE LAM |
Contact Information
| Contractor | Daniel Pascuale; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/26/2025 | Approved | ANTHONY EGSON |
| Underground Mechanical | 6/26/2025 | Partial Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 7/2/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/3/2025 | Conditional Approval | ANTHONY EGSON |
| Deputy Reinf. Concrete | 7/8/2025 | Conditional Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2025 | Partial Approval | ANTHONY EGSON |
| Pre-Inspection | 7/22/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Partial Approval | ANTHONY EGSON |
| Pre-Inspection | 9/22/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Sewer | 10/7/2025 | Partial Approval | ANTHONY EGSON |
| Underground Mechanical | 10/7/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Conditional Approval | JOSEPH MCGARRY |
| Service/Power Release | 10/14/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Underground Mechanical | 10/14/2025 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | No Access for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/5/2025 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/5/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 11/5/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/6/2025 | Approved | ANTHONY EGSON |
| Green Building Rough | 11/6/2025 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 11/6/2025 | Approved | ANTHONY EGSON |
| Insulation | 11/12/2025 | Partial Approval | ANTHONY EGSON |
| Drywall Nailing | 11/14/2025 | Corrections Issued | ANTHONY EGSON |
| Drywall Nailing | 11/18/2025 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 11/18/2025 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 11/20/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Drywall Nailing | 11/21/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/3/2025 | Approved | ARTHUR NEGRETE |
| Sewer | 12/3/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 3/12/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 3/12/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 3/12/2026 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 3/12/2026 | Approved | ARTHUR NEGRETE |
| Final | 3/13/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 3/13/2026 | Approved | ARTHUR NEGRETE |
| Green Building Final | 3/13/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Not Required | ARTHUR NEGRETE |
| Smoke Detectors | 3/13/2026 | Approved | ARTHUR NEGRETE |
| Final | 3/19/2026 | Corrections Issued | ARTHUR NEGRETE |
| Final | 3/23/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Final | 4/2/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Service/Power Release | 4/2/2026 | Approved | ARTHUR NEGRETE |
| Final | 4/7/2026 | OK to Issue CofO | ARTHUR NEGRETE |