628 W 118TH ST 90044

Certificate Information: 628 W 118TH ST 90044

Application / Permit
24010-10000-02438
Plan Check / Job No.
B24LA10907
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert Existing Detached Garage with Addition to Detached Accessory Dwelling Unit per Ordinance . COMPLY WITH DEPARTMENT ORDER effective date 05/16/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 7/15/2024
Issuing Office
Current Status
CofO Issued on 11/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2024 APPLICANT
Assigned to Plan Check Engineer 6/12/2024 GEORGE ALVAREZ
Corrections Issued 6/13/2024 GEORGE ALVAREZ
Plan Check Approved 7/8/2024 FERNANDO FLORES
Issued 7/15/2024 APPLICANT
CofO in Progress 5/30/2025 PAUL REECE
Permit Finaled 11/25/2025 CLAUDIO MORENO
CofO Issued 11/25/2025 CLAUDIO MORENO
Permit Finaled 11/25/2025 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 6/28/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 6/28/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 7/2/2024 JUSTIN BICOL
Sewer availability Cleared 7/2/2024 JUSTIN BICOL

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/7/2024 Approved BRIAN CHRISTIAN
PLUMBING-Rough 12/16/2024 Partial Approval PAUL REECE
Footing/Foundation/Slab 12/19/2024 Approved PAUL REECE
METHANE-Barrier 12/19/2024 Approved PAUL REECE
METHANE-Subgrade 12/19/2024 Approved PAUL REECE
BUILDING-Rough-Frame 1/24/2025 Conditional Approval PAUL REECE
ELECTRICAL-Rough 1/24/2025 Corrections Issued PAUL REECE
Green Building Rough 1/24/2025 Not Ready for Inspection PAUL REECE
MERV13>=Rough 1/24/2025 Conditional Approval PAUL REECE
METHANE-Rough 1/24/2025 Approved PAUL REECE
ELECTRICAL-Rough 2/5/2025 Approved PAUL REECE
PLUMBING-Rough 2/5/2025 Approved KELLY WARNER
BUILDING-Rough-Frame 2/13/2025 Not Ready for Inspection PAUL REECE
Green Building Rough 2/13/2025 Approved PAUL REECE
HVAC-Rough 2/13/2025 Not Ready for Inspection PAUL REECE
Insulation 2/13/2025 Approved KELLY WARNER
MERV13>=Rough 2/13/2025 Not Ready for Inspection PAUL REECE
Drywall Nailing 3/4/2025 Approved KELLY WARNER
Sewer 3/4/2025 Not Ready for Inspection KELLY WARNER
PLUMBING-Final 3/21/2025 Conditional Approval PAUL REECE
BUILDING-Rough-Frame 5/30/2025 Approved PAUL REECE
ELECTRICAL-Final 5/30/2025 Approved PAUL REECE
Final 5/30/2025 OK to Issue CofO PAUL REECE
Green Building Final 5/30/2025 Approved PAUL REECE
HVAC-Final 5/30/2025 Approved PAUL REECE
MERV13>=Final 5/30/2025 Approved PAUL REECE
MERV13>=Rough 5/30/2025 Approved PAUL REECE
PLUMBING-Final 5/30/2025 Approved PAUL REECE
SGSOV-Seismic Gas S/O Valve 5/30/2025 SGSOV Approved PAUL REECE
Smoke Detectors 5/30/2025 Approved PAUL REECE