1666 S WELLINGTON ROAD 90016

Certificate Information: 1666 S WELLINGTON ROAD 90016

Application / Permit
24010-10000-02404
Plan Check / Job No.
B24LA10735
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW DETACHED ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 2/12/2025
Issuing Office
Current Status
CofO Issued on 7/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2024 APPLICANT
Assigned to Plan Check Engineer 8/2/2024 JOHNPAUL ISIP
Corrections Issued 8/3/2024 JOHNPAUL ISIP
Applicant returned to address corrections 10/30/2024 JOHNPAUL ISIP
Plan Check Approved 11/1/2024 JOHNPAUL ISIP
Issued 2/12/2025 APPLICANT
CofO in Progress 7/16/2026 JUSTIN HAWLEY
Permit Finaled 7/16/2026 DEROLD HAUFF
CofO Issued 7/16/2026 DEROLD HAUFF
Permit Finaled 7/16/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/1/2024 AMBER CAMPBELL
Roof/Waste drainage to street Cleared 10/1/2024 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 10/3/2024 WALLIE JONG
Sewer availability Cleared 10/3/2024 WALLIE JONG
CPC Cleared 10/11/2024 SUKI GERSHENHORN
HPOZ Cleared 10/11/2024 SUKI GERSHENHORN

Contact Information

Contractor Gonzalez Mario Construction; Lic. No.: 978711-B       ,
Engineer Gupta,, Raghu; Lic. No.: C87913 6024 BUCKINGHAM PKWY UNIT 16      CULVER CITY, CA 90230
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/17/2025 Corrections Issued WILLIAM SIERRA
METHANE-Barrier 4/17/2025 Approved WILLIAM SIERRA
METHANE-Subgrade 4/17/2025 Approved WILLIAM SIERRA
PLUMBING-Rough 4/17/2025 Corrections Issued WILLIAM SIERRA
Footing/Foundation/Slab 5/5/2025 Approved WILLIAM SIERRA
PLUMBING-Rough 5/5/2025 Partial Approval WILLIAM SIERRA
PLUMBING-Rough 6/13/2025 Partial Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 6/18/2025 Partial Approval JUSTIN HAWLEY
Green Building Rough 6/18/2025 Not Ready for Inspection JUSTIN HAWLEY
Insulation 6/18/2025 Partial Approval JUSTIN HAWLEY
Verify Sprinkler Sign Off 6/18/2025 Not Ready for Inspection JUSTIN HAWLEY
HVAC-Rough 7/28/2025 Partial Approval ARTHUR NEGRETE
PLUMBING-Rough 7/28/2025 Approved ARTHUR NEGRETE
Underground Mechanical 8/13/2025 Corrections Issued JUSTIN HAWLEY
Underground Mechanical 8/21/2025 Approved ARTHUR NEGRETE
Deputy Wood Construction 9/19/2025 Conditional Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 9/30/2025 Approved JUSTIN HAWLEY
Green Building Rough 9/30/2025 Not Ready for Inspection JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 9/30/2025 Approved JUSTIN HAWLEY
Insulation 10/28/2025 Corrections Issued DEVON JACKSON
Interior/Exterior Lathing 10/28/2025 Partial Approval DEVON JACKSON
Insulation 11/5/2025 Approved DEVON JACKSON
Drywall Nailing 11/13/2025 Approved JUSTIN HAWLEY
Green Building Rough 11/13/2025 Approved JUSTIN HAWLEY
Shower Pan 12/2/2025 Approved DEVON JACKSON
Interior/Exterior Lathing 12/12/2025 Approved ALEX COLIN
ELECTRICAL-Rough 2/5/2026 Corrections Issued WILLIAM SIERRA
HVAC-Rough 2/5/2026 Not Ready for Inspection WILLIAM SIERRA
ELECTRICAL-Final 3/5/2026 Approved JUSTIN HAWLEY
HVAC-Final 3/5/2026 Corrections Issued JUSTIN HAWLEY
Service/Power Release 3/5/2026 Approved JUSTIN HAWLEY
Final 7/16/2026 OK to Issue CofO JUSTIN HAWLEY
Green Building Final 7/16/2026 Approved JUSTIN HAWLEY
HVAC-Final 7/16/2026 Approved JUSTIN HAWLEY
PLUMBING-Final 7/16/2026 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 7/16/2026 SGSOV Not Required JUSTIN HAWLEY
Smoke Detectors 7/16/2026 Approved JUSTIN HAWLEY