15964 W GAULT ST 91406
Certificate Information: 15964 W GAULT ST 91406
- Application / Permit
- 24010-10000-02355
- Plan Check / Job No.
- B24LA10551
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ADU PER SB9 AND PER LAMC 12.22 A.33(c) AND (d) Fire Sprinkler
- Permit Issued
- Issued on 12/13/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2024 | KHEDER ALRAZAA |
| Corrections Issued | 6/27/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 7/3/2024 | KEN GILL |
| Building Plans Picked Up | 7/15/2024 | APPLICANT |
| Plan Check Approved | 11/25/2024 | KHEDER ALRAZAA |
| Issued | 12/13/2024 | APPLICANT |
| CofO in Progress | 9/8/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 9/10/2025 | RUBEN SALAS |
| CofO Issued | 9/10/2025 | RUBEN SALAS |
| Permit Finaled | 9/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/12/2024 | KEVIN CHUNG |
| Roof/Waste drainage to street | Cleared | 8/12/2024 | KEVIN CHUNG |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 9/7/2024 | EDGAR ALCARAZ |
Contact Information
| Architect | Hovsepyan,, Ara; Lic. No.: C39097 | 611 N BRAND BLVD #1300 GLENDALE, CA 91203 |
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/3/2025 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/24/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 2/24/2025 | Partial Approval | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 2/26/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 2/26/2025 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 5/5/2025 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/5/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 5/15/2025 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/15/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/30/2025 | Conditional Approval | GAREN HAYRAPETYAN |
| Green Building Rough | 5/30/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 5/30/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 5/30/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Insulation | 6/5/2025 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 6/13/2025 | Approved | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 9/2/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 9/2/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 9/2/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Final | 9/2/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 9/2/2025 | SGSOV No Gas | GAREN HAYRAPETYAN |
| Service/Power Release | 9/2/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 9/2/2025 | Approved | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 9/2/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 9/8/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Service/Power Release | 9/8/2025 | Approved | GAREN HAYRAPETYAN |