15960 W GAULT ST 91406

Certificate Information: 15960 W GAULT ST 91406

Application / Permit
24010-10000-02352
Plan Check / Job No.
B24LA10551
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD PER SB9 (REAR BLDG) Fire sprinkler
Permit Issued
Issued on 12/13/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2024 APPLICANT
Assigned to Plan Check Engineer 6/19/2024 KHEDER ALRAZAA
Corrections Issued 6/27/2024 KHEDER ALRAZAA
Quality Review Completed 7/3/2024 KEN GILL
Building Plans Picked Up 7/15/2024 APPLICANT
Plan Check Approved 11/25/2024 KHEDER ALRAZAA
Issued 12/13/2024 APPLICANT
CofO in Progress 9/8/2025 GAREN HAYRAPETYAN
CofO Issued 9/10/2025 RUBEN SALAS
Permit Finaled 9/10/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/12/2024 KEVIN CHUNG
Roof/Waste drainage to street Cleared 8/12/2024 KEVIN CHUNG
Eng Process Fee Ord 176,300 Cleared 8/19/2024 KEVIN CHUNG
Sewer availability Cleared 8/19/2024 KEVIN CHUNG
Senate Bill 9 Cleared 10/24/2024 YINGSHI HUANG
Hydrant and Access approval Cleared 11/14/2024 KURT CORRAL

Contact Information

Architect Hovsepyan,, Ara; Lic. No.: C39097 611 N BRAND BLVD #1300      GLENDALE, CA 91203
Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/3/2025 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 2/24/2025 Corrections Issued SALVADOR MARTINEZ
Sewer 2/24/2025 Partial Approval SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 2/26/2025 Corrections Issued SALVADOR MARTINEZ
Sewer 2/26/2025 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Partial Approval SALVADOR MARTINEZ
ELECTRICAL-Rough 5/5/2025 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 5/5/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 5/14/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/14/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/21/2025 Partial Approval SALVADOR MARTINEZ
Green Building Rough 5/21/2025 Approved SALVADOR MARTINEZ
HVAC-Rough 5/21/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 5/21/2025 Partial Approval SALVADOR MARTINEZ
PLUMBING-Rough 5/21/2025 Approved SALVADOR MARTINEZ
Verify Sprinkler Sign Off 5/21/2025 Approved SALVADOR MARTINEZ
Insulation 5/23/2025 Approved SALVADOR MARTINEZ
Drywall Nailing 6/4/2025 Corrections Issued MICHAEL CORTEZ
Drywall Nailing 6/13/2025 Approved MICHAEL CORTEZ
BUILDING-Rough-Frame 9/2/2025 Approved GAREN HAYRAPETYAN
Final 9/2/2025 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 9/2/2025 Approved GAREN HAYRAPETYAN
Green Building Final 9/2/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 9/2/2025 SGSOV No Gas GAREN HAYRAPETYAN
Service/Power Release 9/2/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Smoke Detectors 9/2/2025 Approved GAREN HAYRAPETYAN
Final 9/8/2025 OK to Issue CofO GAREN HAYRAPETYAN
Service/Power Release 9/8/2025 Approved GAREN HAYRAPETYAN