328 W 91ST ST 90003

Certificate Information: 328 W 91ST ST 90003

Application / Permit
24010-10000-02349
Plan Check / Job No.
B24LA10526
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER STATE LAW
Permit Issued
Issued on 9/23/2025
Issuing Office
Current Status
CofO Issued on 4/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2024 APPLICANT
Assigned to Plan Check Engineer 6/18/2024 NEHEMIAS RAMOS
Corrections Issued 6/19/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 9/25/2024 JOHN MESIAS
Applicant returned to address corrections 10/31/2024 NEHEMIAS RAMOS
Plan Check Approved 11/4/2024 NEHEMIAS RAMOS
Issued 9/23/2025 APPLICANT
CofO in Progress 4/20/2026 MICHAEL LEWIS
Permit Finaled 4/20/2026 DEROLD HAUFF
CofO Issued 4/20/2026 DEROLD HAUFF
Permit Finaled 4/20/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/7/2024 CELINA MORENO
Roof/Waste drainage to street Cleared 9/7/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/11/2024 CELINA MORENO
Sewer availability Cleared 9/11/2024 CELINA MORENO
Construction near power lines Cleared 10/30/2024 TINA MIRANDA

Contact Information

Contractor Vaisman Construction Inc; Lic. No.: 1076712-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/15/2025 Approved JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 10/20/2025 Corrections Issued JOHN QUINTANILLA
Footing/Foundation/Slab 10/20/2025 Corrections Issued JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 10/22/2025 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 11/3/2025 Partial Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 12/9/2025 Approved JOHN QUINTANILLA
HVAC-Rough 12/9/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 12/9/2025 Approved JOHN QUINTANILLA
Wood Frame 12/9/2025 Not Ready for Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 12/10/2025 Corrections Issued JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Approved JOHN QUINTANILLA
Green Building Rough 12/10/2025 Not Ready for Inspection JOHN QUINTANILLA
MERV13>=Rough 12/10/2025 Approved JOHN QUINTANILLA
Verify Sprinkler Sign Off 12/10/2025 Approved JOHN QUINTANILLA
Insulation 12/17/2025 Not Ready for Inspection DEVON JACKSON
Interior/Exterior Lathing 12/17/2025 Partial Approval DEVON JACKSON
BUILDING-Rough-Frame 12/19/2025 Approved JOHN QUINTANILLA
Green Building Rough 12/19/2025 Approved JOHN QUINTANILLA
Insulation 1/6/2026 Corrections Issued ANTHONY RAMOS
Drywall Nailing 1/12/2026 Corrections Issued JOHN QUINTANILLA
Insulation 1/12/2026 Corrections Issued JOHN QUINTANILLA
Drywall Nailing 1/14/2026 Approved GEM DE OCAMPO
Insulation 1/14/2026 Approved GEM DE OCAMPO
Interior/Exterior Lathing 1/28/2026 Corrections Issued JOHN QUINTANILLA
Underground Mechanical 2/3/2026 Corrections Issued JOHN QUINTANILLA
Underground Mechanical 2/5/2026 Approved JOHN QUINTANILLA
Final 2/27/2026 Not Ready for Inspection JOHN QUINTANILLA
Footing/Foundation/Slab 2/27/2026 Approved JOHN QUINTANILLA
Green Building Final 2/27/2026 Not Ready for Inspection JOHN QUINTANILLA
MERV13>=Final 2/27/2026 Not Ready for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 2/27/2026 SGSOV Not Ready JOHN QUINTANILLA
Service/Power Release 2/27/2026 Not Ready for Inspection JOHN QUINTANILLA
Smoke Detectors 2/27/2026 Not Ready for Inspection JOHN QUINTANILLA
Final 3/4/2026 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 3/4/2026 Approved JOHN QUINTANILLA
MERV13>=Final 3/4/2026 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 3/4/2026 SGSOV Not Required JOHN QUINTANILLA
Service/Power Release 3/4/2026 Approved JOHN QUINTANILLA
Smoke Detectors 3/4/2026 Approved JOHN QUINTANILLA
Final 3/9/2026 Partial Approval JOHN QUINTANILLA
Final 3/16/2026 Conditional Approval JOHN QUINTANILLA
Final 4/2/2026 Corrections Issued JOHN QUINTANILLA
Final 4/17/2026 OK to Issue CofO MICHAEL LEWIS