936 N ORLANDO AVE 90069
Certificate Information: 936 N ORLANDO AVE 90069
- Application / Permit
- 24010-10000-02343
- Plan Check / Job No.
- B24LA10499
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New detached two story ADU PER LAMC 12.22 A.33(c) AND (d)'
- Permit Issued
- Issued on 9/19/2024
- Issuing Office
- Current Status
- CofO Issued on 7/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2024 | KHEDER ALRAZAA |
| Corrections Issued | 6/21/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 8/1/2024 | HERNAN ARREOLA |
| Plan Check Approved | 9/16/2024 | KHEDER ALRAZAA |
| Issued | 9/19/2024 | APPLICANT |
| CofO in Progress | 7/10/2025 | JOSE MACIAS |
| Permit Finaled | 7/15/2025 | DEROLD HAUFF |
| CofO Issued | 7/15/2025 | DEROLD HAUFF |
| Permit Finaled | 7/15/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/30/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 7/30/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 7/31/2024 | JUSTIN BICOL |
Contact Information
| Contractor | R G Remodel; Lic. No.: 1074569-B | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: NA56881 | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/26/2024 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 10/1/2024 | Approved | JOSE MACIAS |
| Deputy Drilled-In Anchors | 10/4/2024 | Conditional Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 10/8/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2024 | Approved | JOSE MACIAS |
| Rough-Elec/Plmb/HVAC | 12/24/2024 | Corrections Issued | JOSE MACIAS |
| Rough-Elec/Plmb/HVAC | 1/14/2025 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 1/21/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 1/21/2025 | Approved | JOSE MACIAS |
| Verify Sprinkler Sign Off | 1/21/2025 | Approved | JOSE MACIAS |
| Insulation | 1/27/2025 | Corrections Issued | JOSE MACIAS |
| Drywall Nailing | 2/10/2025 | Approved | JOSE MACIAS |
| Shower Pan | 2/19/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 5/22/2025 | Corrections Issued | JOSE MACIAS |
| HVAC-Final | 5/22/2025 | Approved | JOSE MACIAS |
| PLUMBING-Final | 5/22/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 6/6/2025 | Approved | JOSE MACIAS |
| Final | 6/6/2025 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Final | 6/6/2025 | Approved | JOSE MACIAS |
| PLUMBING-Final | 6/6/2025 | Approved | JOSE MACIAS |
| Verify Rec and Parks Fee Memo | 6/6/2025 | Approved | JOSE MACIAS |
| Green Building Final | 6/24/2025 | Approved | JOSE MACIAS |
| Final | 7/8/2025 | Corrections Issued | JOSE MACIAS |
| Final | 7/9/2025 | OK to Issue CofO | JOSE MACIAS |
| Footing/Foundation/Slab | 7/9/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 7/9/2025 | SGSOV Approved | JOSE MACIAS |
| Service/Power Release | 7/9/2025 | Approved | JOSE MACIAS |
| Smoke Detectors | 7/9/2025 | Approved | JOSE MACIAS |