125-127 W 97TH ST 90003
Certificate Information: 125-127 W 97TH ST 90003
- Application / Permit
- 24010-10000-02333
- Plan Check / Job No.
- B24LA10457
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Eplan NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE( NFPA-13D Fire Sprinkler System Thru-Out).
- Permit Issued
- Issued on 12/11/2024
- Issuing Office
- Current Status
- CofO Issued on 6/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2024 | GARO TELMI |
| Corrections Issued | 6/10/2024 | GARO TELMI |
| Quality Review Completed | 6/18/2024 | CHAD DOI |
| Plan Check Approved | 11/5/2024 | GARO TELMI |
| Issued | 12/11/2024 | APPLICANT |
| CofO in Progress | 6/21/2025 | JOHN KLARIN |
| Permit Finaled | 6/23/2025 | ANSON MAGLASANG |
| CofO Issued | 6/23/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 7/25/2024 | SARAH YOUSSEF |
| Address approval | Cleared | 8/3/2024 | CELINA MORENO |
| Permit | Cleared | 8/3/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2024 | CELINA MORENO |
| Sewer availability | Cleared | 8/13/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 8/14/2024 | CELINA MORENO |
| Trees in Parkway | Cleared | 8/26/2024 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 9/19/2024 | LAVEON RIDER |
| SB8 RUD | Cleared | 10/21/2024 | ASHLEY MEDINA |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/8/2025 | Approved | BEN MOLSTAD |
| Underground Mechanical | 1/17/2025 | Partial Approval | ANTHONY EGSON |
| Wood Frame | 1/17/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 1/21/2025 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2025 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2025 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 4/3/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/3/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 4/3/2025 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 4/3/2025 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 4/3/2025 | Approved | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 4/3/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 4/4/2025 | No Access for Inspection | ANTHONY EGSON |
| Insulation | 4/7/2025 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/9/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/9/2025 | Approved | BEN MOLSTAD |
| Green Building Rough | 4/9/2025 | Approved | BEN MOLSTAD |
| HVAC-Rough | 4/9/2025 | Approved | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 4/9/2025 | Approved | BEN MOLSTAD |
| Insulation | 4/10/2025 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/18/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 4/18/2025 | Approved | ANTHONY EGSON |
| Green Building Rough | 4/18/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/18/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 6/13/2025 | Approved | JOSEPH MCGARRY |
| Final | 6/13/2025 | Corrections Issued | JOSEPH MCGARRY |
| HVAC-Final | 6/13/2025 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 6/13/2025 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 6/13/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Smoke Detectors | 6/13/2025 | Approved | JOSEPH MCGARRY |
| Final | 6/16/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Final | 6/16/2025 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 6/16/2025 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 6/16/2025 | SGSOV Not Required | JOSEPH MCGARRY |
| Service/Power Release | 6/16/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Smoke Detectors | 6/16/2025 | Approved | JOSEPH MCGARRY |
| Final | 6/20/2025 | OK to Issue CofO | JOHN KLARIN |
| Service/Power Release | 6/20/2025 | Approved | JOHN KLARIN |