6711 N KRAFT AVE 91606

Certificate Information: 6711 N KRAFT AVE 91606

Application / Permit
24010-10000-02320
Plan Check / Job No.
B24LA10401
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU per LAMC 12.22A.33 (c) and (d)
Permit Issued
Issued on 9/10/2025
Issuing Office
Valley
Current Status
Issued on 9/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/31/2024 APPLICANT
Assigned to Plan Check Engineer 6/19/2024 MARCELA FRANQUEZ
Corrections Issued 6/28/2024 MARCELA FRANQUEZ
Quality Review Completed 7/3/2024 KEN GILL
Building Plans Picked Up 7/5/2024 APPLICANT
Plan Check Approved 5/1/2025 MARCELA FRANQUEZ
Issued 9/10/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/20/2024 TAL SHEMEN
Roof/Waste drainage to street Cleared 7/20/2024 TAL SHEMEN
Sewer availability Cleared 7/20/2024 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 7/23/2024 TAL SHEMEN
Tenant Habitability Plan Cleared 7/25/2024 HUGO GARRIDO GARZA

Contact Information

Contractor Red Fox Construction Inc; Lic. No.: 1053042-B 1465 TAMARIND AVENUE #550      HOLLYWOOD, CA 90028

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/24/2025 Not Ready for Inspection JOSE AVILA
Underground Mechanical 10/24/2025 Partial Approval JOSE AVILA
Footing/Foundation/Slab 12/9/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 12/15/2025 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/30/2025 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/18/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Sewer 2/18/2026 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 2/18/2026 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 2/23/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/23/2026 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 4/21/2026 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/21/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 4/21/2026 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/22/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/27/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/4/2026 Approved GAREN HAYRAPETYAN
Green Building Rough 5/4/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Insulation 5/4/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 5/4/2026 Approved GAREN HAYRAPETYAN
Green Building Rough 5/12/2026 Approved GAREN HAYRAPETYAN
Insulation 5/12/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 5/12/2026 Partial Approval GAREN HAYRAPETYAN
Drywall Nailing 5/15/2026 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 5/26/2026 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 5/26/2026 Approved ROBERTO PALACIOS-LOPEZ