2841 E FOLSOM ST 90033

Certificate Information: 2841 E FOLSOM ST 90033

Application / Permit
24010-10000-02304
Plan Check / Job No.
B24LA10277
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1) NEW ONE STORY DETACHED ADU W/ ATTACHED ONE CAR GARAGE PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 2/27/2025
Issuing Office
Metro
Current Status
CofO Issued on 10/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2024 APPLICANT
Assigned to Plan Check Engineer 6/19/2024 SERGIO GUTIERREZ
Corrections Issued 7/3/2024 SERGIO GUTIERREZ
Quality Review Completed 7/12/2024 KEN GILL
Building Plans Picked Up 8/8/2024 APPLICANT
Applicant returned to address corrections 10/24/2024 SERGIO GUTIERREZ
Applicant returned to address corrections 2/25/2025 SERGIO GUTIERREZ
Plan Check Approved 2/27/2025 SERGIO GUTIERREZ
Issued 2/27/2025 APPLICANT
CofO in Progress 10/28/2025 ALIZAH MAYAGOITIA
Permit Finaled 10/29/2025 DEROLD HAUFF
CofO Issued 10/29/2025 DEROLD HAUFF
Permit Finaled 10/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/15/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 11/15/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 1/10/2025 CHRISTINA BRACO
Hydrant and Access approval Cleared 1/17/2025 JERRY KAO
Sewer availability Cleared 1/22/2025 CHRISTINA BRACO
Clean Up Green Up Cleared 1/29/2025 JASON CHAN
GPI Written Notices Cleared 2/25/2025 SERGIO GUTIERREZ
Grading Pre-Inspection Cleared 2/25/2025 SERGIO GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Evangelista,, Gil Viernes; Lic. No.: S2422 749 N FEATHERWOOD DR      DIAMOND BAR, CA 91765

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/3/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
METHANE-Barrier 3/3/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
METHANE-Subgrade 3/3/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 3/7/2025 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 3/7/2025 Partial Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 3/10/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Deputy Methane Barrier 4/1/2025 Conditional Approval JOSH MEISTER
Footing/Foundation/Slab 4/1/2025 Approved ALIZAH MAYAGOITIA
METHANE-Barrier 4/1/2025 Approved ALIZAH MAYAGOITIA
METHANE-Subgrade 4/1/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 5/1/2025 Corrections Issued OSVALDO PARAMO
Green Building Rough 5/1/2025 Not Ready for Inspection OSVALDO PARAMO
METHANE-Rough 5/1/2025 Not Ready for Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 5/1/2025 Not Ready for Inspection OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 5/5/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 5/7/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 5/7/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
METHANE-Rough 5/7/2025 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 5/7/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/21/2025 Partial Approval ANTHONY RAMOS
Insulation 5/28/2025 Corrections Issued REGINA MENDEZ
Insulation 6/2/2025 Not Ready for Inspection ANTHONY RAMOS
Drywall Nailing 6/13/2025 Approved ALIZAH MAYAGOITIA
Insulation 6/13/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 7/7/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 7/7/2025 Approved JUSTIN HAWLEY
Underground Mechanical 8/1/2025 Partial Approval ANTHONY RAMOS
PLUMBING-Rough 8/7/2025 Approved ANTHONY RAMOS
BUILDING-Rough-Frame 8/26/2025 Approved ALIZAH MAYAGOITIA
Final 8/26/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 8/26/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 8/26/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 8/26/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 9/15/2025 Corrections Issued BRENDAN MORELLI
HVAC-Final 9/15/2025 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 9/19/2025 No Access for Inspection FREDDIE RIVERA
ELECTRICAL-Final 9/23/2025 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Final 9/25/2025 Approved ALIZAH MAYAGOITIA
Final 9/25/2025 Conditional Approval ALIZAH MAYAGOITIA
Green Building Final 9/25/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/25/2025 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 9/25/2025 Approved ALIZAH MAYAGOITIA
Final 10/24/2025 Conditional Approval ALIZAH MAYAGOITIA
Final 10/27/2025 OK to Issue CofO ALIZAH MAYAGOITIA