2841 E FOLSOM ST 90033
Certificate Information: 2841 E FOLSOM ST 90033
- Application / Permit
- 24010-10000-02304
- Plan Check / Job No.
- B24LA10277
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1) NEW ONE STORY DETACHED ADU W/ ATTACHED ONE CAR GARAGE PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/27/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2024 | SERGIO GUTIERREZ |
| Corrections Issued | 7/3/2024 | SERGIO GUTIERREZ |
| Quality Review Completed | 7/12/2024 | KEN GILL |
| Building Plans Picked Up | 8/8/2024 | APPLICANT |
| Applicant returned to address corrections | 10/24/2024 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 2/25/2025 | SERGIO GUTIERREZ |
| Plan Check Approved | 2/27/2025 | SERGIO GUTIERREZ |
| Issued | 2/27/2025 | APPLICANT |
| CofO in Progress | 10/28/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 10/29/2025 | DEROLD HAUFF |
| CofO Issued | 10/29/2025 | DEROLD HAUFF |
| Permit Finaled | 10/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 11/15/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2025 | CHRISTINA BRACO |
| Hydrant and Access approval | Cleared | 1/17/2025 | JERRY KAO |
| Sewer availability | Cleared | 1/22/2025 | CHRISTINA BRACO |
| Clean Up Green Up | Cleared | 1/29/2025 | JASON CHAN |
| GPI Written Notices | Cleared | 2/25/2025 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 2/25/2025 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/3/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| METHANE-Barrier | 3/3/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| METHANE-Subgrade | 3/3/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 3/7/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/7/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 3/10/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Deputy Methane Barrier | 4/1/2025 | Conditional Approval | JOSH MEISTER |
| Footing/Foundation/Slab | 4/1/2025 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Barrier | 4/1/2025 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Subgrade | 4/1/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/1/2025 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 5/1/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| METHANE-Rough | 5/1/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 5/1/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 5/5/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/7/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 5/7/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| METHANE-Rough | 5/7/2025 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 5/7/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 5/21/2025 | Partial Approval | ANTHONY RAMOS |
| Insulation | 5/28/2025 | Corrections Issued | REGINA MENDEZ |
| Insulation | 6/2/2025 | Not Ready for Inspection | ANTHONY RAMOS |
| Drywall Nailing | 6/13/2025 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 6/13/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 7/7/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 7/7/2025 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 8/1/2025 | Partial Approval | ANTHONY RAMOS |
| PLUMBING-Rough | 8/7/2025 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 8/26/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/26/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 8/26/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/26/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 8/26/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/26/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 9/15/2025 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Final | 9/15/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 9/19/2025 | No Access for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 9/23/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 9/25/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 9/25/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Green Building Final | 9/25/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 9/25/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 9/25/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/24/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 10/27/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |