8343 S KITTYHAWK AVE 90045
Certificate Information: 8343 S KITTYHAWK AVE 90045
- Application / Permit
- 24010-10000-02297
- Plan Check / Job No.
- B24LA10232
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-PLAN. NEW (2) UNIT 2 STORY DETACHED ADU PER CA GOVT CODE 65852.2(E)(1)(D) AND 65852.2 (C)(2)(D)
- Permit Issued
- Issued on 9/20/2024
- Issuing Office
- Current Status
- CofO Issued on 5/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2024 | JAD BASMA |
| Corrections Issued | 6/15/2024 | JAD BASMA |
| Quality Review Completed | 7/10/2024 | MICHAEL PEREZ |
| Applicant returned to address corrections | 8/1/2024 | JAD BASMA |
| Plan Check Approved | 8/8/2024 | JAD BASMA |
| Issued | 9/20/2024 | APPLICANT |
| CofO in Progress | 4/11/2025 | ANDREW BEELI |
| Permit Finaled | 5/7/2025 | CLAUDIO MORENO |
| CofO Issued | 5/7/2025 | CLAUDIO MORENO |
| Permit Finaled | 5/7/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 6/24/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 6/24/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2024 | DARIN LAM |
| Sewer availability | Cleared | 6/26/2024 | DARIN LAM |
| Specific Plan | Cleared | 6/27/2024 | RICHARD WOO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/25/2024 | Approved | ANDREW BEELI |
| Excavation/Setback/Form/Re-Bar | 10/4/2024 | Approved | ANDREW BEELI |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Approved | ANDREW BEELI |
| Deputy Wood Construction | 11/21/2024 | Partial Approval | ANDREW BEELI |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2024 | Approved | ANDREW BEELI |
| BUILDING-Rough-Frame | 12/6/2024 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Rough | 12/6/2024 | Not Ready for Inspection | ANDREW BEELI |
| Rough-Elec/Plmb/HVAC | 12/6/2024 | Approved | ANDREW BEELI |
| Verify Sprinkler Sign Off | 12/6/2024 | Not Ready for Inspection | ANDREW BEELI |
| BUILDING-Rough-Frame | 12/12/2024 | Approved | ANDREW BEELI |
| Green Building Rough | 12/12/2024 | Approved | ANDREW BEELI |
| Rough-Elec/Plmb/HVAC | 12/12/2024 | Approved | ANDREW BEELI |
| Verify Sprinkler Sign Off | 12/12/2024 | Approved | ANDREW BEELI |
| Insulation | 12/31/2024 | Approved | ANDREW BEELI |
| Interior/Exterior Lathing | 12/31/2024 | Approved | ANDREW BEELI |
| Drywall Nailing | 1/10/2025 | Not Ready for Inspection | ANDREW BEELI |
| Interior/Exterior Lathing | 1/10/2025 | Not Ready for Inspection | ANDREW BEELI |
| Drywall Nailing | 1/14/2025 | Approved | ANDREW BEELI |
| Interior/Exterior Lathing | 1/14/2025 | Approved | ANDREW BEELI |
| Final | 3/14/2025 | Not Ready for Inspection | ANDREW BEELI |
| Footing/Foundation/Slab | 3/14/2025 | Approved | ANDREW BEELI |
| Green Building Final | 3/14/2025 | Corrections Issued | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 3/14/2025 | SGSOV No Gas | ANDREW BEELI |
| Smoke Detectors | 3/14/2025 | Not Ready for Inspection | ANDREW BEELI |
| Final | 3/18/2025 | Corrections Issued | ANDREW BEELI |
| Green Building Final | 3/18/2025 | Approved | ANDREW BEELI |
| Service/Power Release | 3/18/2025 | Approved | ANDREW BEELI |
| Smoke Detectors | 3/18/2025 | Approved | ANDREW BEELI |
| Final | 3/28/2025 | Conditional Approval | ANDREW BEELI |
| Final | 4/11/2025 | OK to Issue CofO | ANDREW BEELI |