10818 W WESTMINSTER AVE 90034

Certificate Information: 10818 W WESTMINSTER AVE 90034

Application / Permit
24010-10000-02277
Plan Check / Job No.
B24LA10120
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN New construction detached ADU at rear of lot per state law. All work done per an engineered design. NFPA-13D fire sprinklers thru-out.
Permit Issued
Issued on 10/11/2024
Issuing Office
Current Status
Issued on 10/11/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/28/2024 APPLICANT
Assigned to Plan Check Engineer 6/3/2024 DANIEL SMILEY
Corrections Issued 6/4/2024 DANIEL SMILEY
Plan Check Approved 10/11/2024 DANIEL SMILEY
Issued 10/11/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/10/2024 DARIN LAM
Roof/Waste drainage to street Cleared 6/10/2024 DARIN LAM
Grading Pre-Inspection Cleared 6/13/2024 LANNY MERRICK
Eng Process Fee Ord 176,300 Cleared 6/15/2024 DARIN LAM
Sewer availability Cleared 6/15/2024 DARIN LAM
Specific Plan Cleared 6/20/2024 JOSHUA JONES
Construction near power lines Cleared 10/7/2024 RIDWAN HARDY
Construction within easement Cleared 10/7/2024 RIDWAN HARDY
GPI Written Notices Cleared 10/11/2024 DANIEL SMILEY

Contact Information

Contractor Bless It Construction Inc; Lic. No.: 1048746-B       ,
Engineer Koma,, Shahram Javadi; Lic. No.: NA69497       ,
Engineer Vassallo,, Christopher W.; Lic. No.: L8418 28441 HIGHRIDGE RD 230      ROLLING HILLS ESTATES, CA 90274

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/31/2024 Approved DANIEL VERA
Footing/Foundation/Slab 11/4/2024 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 12/6/2024 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 2/18/2025 Not Ready for Inspection DANIEL VERA
Deputy Wood Construction 2/18/2025 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 2/18/2025 Conditional Approval DANIEL VERA
Green Building Rough 2/18/2025 Not Ready for Inspection DANIEL VERA
Verify Sprinkler Sign Off 2/18/2025 Not Ready for Inspection DANIEL VERA
Special/Order Compliance 3/11/2025 Partial Inspection MICHAEL PELHAM
ELECTRICAL-Rough 4/18/2025 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 4/18/2025 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 4/18/2025 Approved ARAM AVEDISIAN
Wood Frame 4/18/2025 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 4/30/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 4/30/2025 Approved WILBER ROSALES
Green Building Rough 4/30/2025 Approved WILBER ROSALES
HVAC-Rough 4/30/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 4/30/2025 Approved WILBER ROSALES
Verify Sprinkler Sign Off 4/30/2025 Approved WILBER ROSALES
Insulation 5/2/2025 Corrections Issued WILBER ROSALES
Insulation 5/7/2025 Approved WILBER ROSALES
Drywall Nailing 5/12/2025 Approved ARAM AVEDISIAN
Shower Pan 5/12/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 5/15/2025 Approved BOBBY KEY
ELECTRICAL-Final 4/21/2026 Approved RYAN SALAZAR
HVAC-Final 4/21/2026 Approved RYAN SALAZAR
PLUMBING-Final 4/21/2026 Approved RYAN SALAZAR