18250 W STRATHERN ST 91335

Certificate Information: 18250 W STRATHERN ST 91335

Application / Permit
24010-10000-02161
Plan Check / Job No.
B24LA09651
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(ePlan) New 2-Story DETACHED A.D.U. PER LAMC 12.22 A.33 (c) and (d).
Permit Issued
Issued on 9/24/2024
Issuing Office
Current Status
CofO Issued on 10/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2024 APPLICANT
Assigned to Plan Check Engineer 6/6/2024 ADRIANA LOPEZ
Corrections Issued 6/24/2024 ADRIANA LOPEZ
Quality Review Completed 7/5/2024 SINA KHOSRAVI
Applicant returned to address corrections 8/15/2024 ADRIANA LOPEZ
Applicant returned to address corrections 9/3/2024 YOUNG KIM
Plan Check Approved 9/24/2024 ADRIANA LOPEZ
Issued 9/24/2024 APPLICANT
CofO in Progress 10/8/2025 ARUTYUN MADATYAN
Permit Finaled 10/9/2025 JOHN JANSON
CofO Issued 10/9/2025 JOHN JANSON
Permit Finaled 10/9/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/6/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/6/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/8/2024 CARLOS AGUILERA
Sewer availability Cleared 7/8/2024 CARLOS AGUILERA
ZA Case Cleared 7/9/2024 ALEX VELA
ZA Case Cleared 7/9/2024 ALEX VELA
ZA Case Cleared 7/9/2024 ALEX VELA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/26/2024 Partial Approval JEFFREY BULL
Footing/Foundation/Slab 10/2/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 10/24/2024 Partial Approval JEFFREY BULL
BUILDING-Rough-Frame 11/12/2024 Partial Approval ARUTYUN MADATYAN
ELECTRICAL-Rough 11/12/2024 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Approved ARUTYUN MADATYAN
Green Building Rough 11/12/2024 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Rough 11/12/2024 Approved ARUTYUN MADATYAN
PLUMBING-Rough 11/12/2024 Approved ARUTYUN MADATYAN
Verify Sprinkler Sign Off 11/12/2024 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 12/6/2024 Approved ARUTYUN MADATYAN
Green Building Rough 12/6/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 12/6/2024 Partial Approval ARUTYUN MADATYAN
Insulation 4/8/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 4/8/2025 Partial Approval ARUTYUN MADATYAN
Shower Pan 4/8/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 4/21/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 5/7/2025 Partial Approval ARUTYUN MADATYAN
PLUMBING-Rough 5/7/2025 Partial Approval ARUTYUN MADATYAN
Sewer 5/7/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 10/6/2025 Approved ARUTYUN MADATYAN
Final 10/6/2025 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 10/6/2025 Approved ARUTYUN MADATYAN
HVAC-Final 10/6/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 10/6/2025 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 10/6/2025 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 10/6/2025 Approved ARUTYUN MADATYAN
Smoke Detectors 10/6/2025 Approved ARUTYUN MADATYAN