3454 S TILDEN AVE 90034
Certificate Information: 3454 S TILDEN AVE 90034
- Application / Permit
- 24010-10000-02136
- Plan Check / Job No.
- B24LA09570
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- NEW 22'X10' DETACHED LAUNDRY AND STORAGE STRUCTURE
- Permit Issued
- Issued on 10/25/2024
- Issuing Office
- Current Status
- CofO Issued on 3/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 5/25/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 10/17/2024 | ALEC MOUSAKHANIAN |
| Issued | 10/25/2024 | APPLICANT |
| CofO in Progress | 3/13/2025 | DANIEL VERA |
| CofO Issued | 3/15/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/15/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 7/5/2024 | DARIN LAM |
| Specific Plan | Cleared | 7/22/2024 | FREDDY GARCIA |
| Grading Pre-Inspection | Cleared | 7/31/2024 | ALEXANDER HELFER |
| Construction near power lines | Cleared | 10/7/2024 | RIDWAN HARDY |
Contact Information
| Architect | Tamm-Seitz,, Aleksander; Lic. No.: NA34163 | , |
| Contractor | Marva General Construction; Lic. No.: 853173-B | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/31/2024 | Approved | DANIEL VERA |
| Underground Mechanical | 10/31/2024 | Approved | DANIEL VERA |
| Footing/Foundation/Slab | 11/7/2024 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 12/5/2024 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 12/5/2024 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2024 | Approved | DANIEL VERA |
| Green Building Rough | 12/5/2024 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 12/5/2024 | Approved | DANIEL VERA |
| PLUMBING-Rough | 12/5/2024 | Approved | DANIEL VERA |
| Verify Sprinkler Sign Off | 12/5/2024 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 12/9/2024 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 12/9/2024 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 12/9/2024 | Approved | MICHAEL ALLEN |
| Wood Frame | 12/9/2024 | Approved | MICHAEL ALLEN |
| Insulation | 12/11/2024 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 12/12/2024 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 2/20/2025 | Approved | DANIEL VERA |
| Final | 2/20/2025 | Corrections Issued | DANIEL VERA |
| Green Building Final | 2/20/2025 | Approved | DANIEL VERA |
| Green Building Rough | 2/20/2025 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 2/20/2025 | SGSOV Approved | DANIEL VERA |
| Service/Power Release | 2/20/2025 | Not Required | DANIEL VERA |
| Smoke Detectors | 2/20/2025 | Approved | DANIEL VERA |
| Final | 3/12/2025 | OK to Issue CofO | DANIEL VERA |