4952 N COLUMBUS AVE 91403
Certificate Information: 4952 N COLUMBUS AVE 91403
- Application / Permit
- 24010-10000-02126
- Plan Check / Job No.
- B24LA09530
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY DWELLING PER SB9 TWO UNIT DEVELOPMENT (2-STORY)
- Permit Issued
- Issued on 11/18/2025
- Issuing Office
- Current Status
- Issued on 11/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2024 | CARLOS MONTES |
| Corrections Issued | 6/4/2024 | CARLOS MONTES |
| Quality Review Completed | 6/12/2024 | GARO TELMI |
| Plan Check Approved | 12/5/2024 | CARLOS MONTES |
| Issued | 11/18/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 7/1/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/1/2024 | BIAINA HARITUNIAN |
| Senate Bill 9 | Cleared | 7/10/2024 | ALEX VELA |
| ZI | Cleared | 7/10/2024 | ALEX VELA |
| Permit | Cleared | 8/1/2024 | BIAINA HARITUNIAN |
| Trees in Parkway | Cleared | 8/1/2024 | DYNL MIRANDA |
| Hydrant and Access approval | Cleared | 9/3/2024 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 5/9/2025 | ENRIQUE ACOSTA |
Contact Information
| Contractor | Building La; Lic. No.: 1098623-B | , |
| Engineer | Ebrahimi,, Amirhosin; Lic. No.: C92049 | 8619 RESEDA BLVD UNIT 304B NORTHRIDGE, CA 91324 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/25/2025 | No Access for Inspection | MISAEL ESPARZA |
| Pre-Inspection | 11/25/2025 | No Access for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 11/26/2025 | Corrections Issued | MISAEL ESPARZA |
| Pre-Inspection | 11/26/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 12/3/2025 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 12/10/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Pre-Inspection | 12/10/2025 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 12/19/2025 | Order to Comply Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 12/22/2025 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2026 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2026 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/13/2026 | Partial Inspection | MICHAEL CORTEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2026 | Approved | MICHAEL CORTEZ |
| Green Building Rough | 4/13/2026 | Not Ready for Inspection | MICHAEL CORTEZ |
| MERV13>=Rough | 4/13/2026 | Approved | MICHAEL CORTEZ |
| Rough-Elec/Plmb/HVAC | 4/13/2026 | Partial Approval | MICHAEL CORTEZ |
| Verify Sprinkler Sign Off | 4/13/2026 | Approved | MICHAEL CORTEZ |
| Deputy Wood Construction | 4/20/2026 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/7/2026 | Conditional Approval | MICHAEL CORTEZ |
| Green Building Rough | 5/7/2026 | Not Ready for Inspection | MICHAEL CORTEZ |
| Rough-Elec/Plmb/HVAC | 5/7/2026 | Approved | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 5/18/2026 | Approved | MISAEL ESPARZA |
| Green Building Rough | 5/18/2026 | Approved | MISAEL ESPARZA |
| Insulation | 5/18/2026 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/18/2026 | Partial Approval | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 5/18/2026 | Approved | MISAEL ESPARZA |
| Insulation | 5/27/2026 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 6/4/2026 | Approved | MISAEL ESPARZA |