4261 N VANTAGE AVE 91604
Certificate Information: 4261 N VANTAGE AVE 91604
- Application / Permit
- 24010-10000-02092
- Plan Check / Job No.
- B24LA08836
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan New 15' 2" x 41' one story ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g). NFPA 13D sprinkler required. All work done per engineer.
- Permit Issued
- Issued on 8/8/2024
- Issuing Office
- Current Status
- CofO Issued on 8/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | NAREG ATARIAN |
| Corrections Issued | 5/19/2024 | NAREG ATARIAN |
| Quality Review Completed | 5/21/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 7/18/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 7/26/2024 | NAREG ATARIAN |
| Plan Check Approved | 7/29/2024 | NAREG ATARIAN |
| Issued | 8/8/2024 | APPLICANT |
| CofO in Progress | 7/23/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
| CofO Issued | 8/5/2025 | RUBEN SALAS |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/30/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 5/30/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/30/2024 | BIAINA HARITUNIAN |
| ZI | Cleared | 6/4/2024 | STEVEN WECHSLER |
| Construction near power lines | Cleared | 7/15/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/23/2024 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 8/23/2024 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 9/4/2024 | Approved | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 9/9/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 9/12/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/21/2024 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 10/21/2024 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 10/25/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 11/6/2024 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 11/6/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/14/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/14/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 11/14/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/21/2024 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/21/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 11/26/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Shower Pan | 11/26/2024 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 12/23/2024 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 12/23/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 1/8/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 7/2/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Final | 7/2/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 7/2/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 7/16/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 7/16/2025 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV Not Required | CHRISTOPHE COCHRAN |
| Service/Power Release | 7/16/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 7/16/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 7/18/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 7/18/2025 | Approved | CHRISTOPHE COCHRAN |