1432 S BEVERLY DR 1-48 90035
Certificate Information: 1432 S BEVERLY DR 1-48 90035
- Application / Permit
- 24010-10000-02085
- Plan Check / Job No.
- B24LA09302
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- eplan - NEW 7 STORY 48 UNITS (37 LI, 10 MI) AFFORDABLE HOUSING APARTMENT TO INCLUDE 5 STORY TYPE IIIA APARTMENT OVER 2 STORY TYPE IA APARTMENT/PARKING, USING 12.22.A.25 INCENTIVES
- Permit Issued
- Issued on 7/22/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 7/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | VU NGUYEN |
| Assigned to Zoning Architect | 5/23/2024 | MEGAN KOLP |
| Corrections Issued | 5/24/2024 | VU NGUYEN |
| Quality Review Completed | 5/28/2024 | EUGENE BARBEAU |
| Plan Check Approved | 7/18/2025 | STARR CHEN |
| Issued | 7/22/2025 | APPLICANT |
Permit Application Clearance Information
| Highway dedication | Cleared | 8/23/2024 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2024 | DARIN LAM |
| Address approval | Cleared | 11/2/2024 | DARIN LAM |
| Sewer availability | Cleared | 12/8/2024 | LIAM ODONOVAN |
| Encroachment in public way | Cleared | 12/10/2024 | SAUL GARCIA |
| Low Impact Development (LID) | Cleared | 1/2/2025 | ERNEST TSE |
| Green Code | Cleared | 1/5/2025 | VU NGUYEN |
| Roof/Waste drainage to street | Cleared | 1/15/2025 | LIAM ODONOVAN |
| GPI Written Notices | Cleared | 2/1/2025 | VU NGUYEN |
| Grading Pre-Inspection | Cleared | 2/1/2025 | VU NGUYEN |
| Trees in Parkway | Cleared | 3/9/2025 | BRANDON WONG |
| Permit | Cleared | 3/10/2025 | DARIN LAM |
| Hydrant and Access approval | Cleared | 4/7/2025 | LAVEON RIDER |
| Miscellaneous | Cleared | 4/9/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 4/9/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 4/9/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 4/9/2025 | DANIEL CORONADO |
| Density Bonus | Cleared | 4/30/2025 | KENNETH LE |
| SB8 RUD | Cleared | 4/30/2025 | KENNETH LE |
| Demo/Removal of Rental Units | Cleared | 5/1/2025 | EDWARD JACOBS |
| DAS Clearance | Cleared | 6/5/2025 | VU NGUYEN |
| "Q" conditions | Cleared | 6/20/2025 | DANIEL CORONADO |
| Frnt yard landscape/Water mgmt | Cleared | 6/20/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 6/20/2025 | DANIEL CORONADO |
| Zoning Plan Check | Cleared | 7/2/2025 | MEGAN KOLP |
| Fire Marshal Fire Life Safety | Cleared | 7/7/2025 | MENOA AGHAJANI |
Contact Information
| Architect | Brumer,, Aaron Jason; Lic. No.: C30005 | 3330 CAHUENGA BLVD W SUITE 507 LOS ANGELES, CA 90068 |
| Contractor | Mbg Construction Inc; Lic. No.: 1098398-B | , |
| Engineer | Aboufadel,, Nicholas Fadlo; Lic. No.: C50588 | 4000 PARK NEWPORT SUITE 303 NEWPORT BEACH, CA 92660 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 347 ROBERTSON BLVD BEVERLY HILLS, CA 90211 |
| Engineer | Obando,, Gaspar Eduardo; Lic. No.: C71382 | 3101 OCEAN PARK BLVD STE 100, PMB 122 SANTA MONICA, CA 90405 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Soliman,, John; Lic. No.: C80833 | 13785 PELICAN DR RANCHO CUCAMONGA, CA 91739 |
Inspector Information
| PAUL DAVIDSON, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2026 |
Inspection Request History
| Footing/Foundation/Slab | 10/3/2025 | Partial Approval | DANIEL VARNUM |
| METHANE-Barrier | 10/3/2025 | Conditional Approval | DANIEL VARNUM |
| METHANE-Subgrade | 10/3/2025 | Conditional Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 10/14/2025 | Conditional Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 10/15/2025 | Conditional Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 10/16/2025 | Conditional Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 10/20/2025 | Conditional Approval | DANIEL VARNUM |
| Reinforced Concrete Frame | 10/21/2025 | Partial Approval | DANIEL VARNUM |
| Deputy Shotcrete | 10/22/2025 | Approved | VASIL MIHALEV |
| Deputy Shotcrete | 10/22/2025 | Conditional Approval | PAUL DAVIDSON |
| Deputy Shotcrete | 10/22/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Reinf. Concrete | 12/11/2025 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 12/17/2025 | Partial Approval | PAUL DAVIDSON |
| METHANE-Barrier | 12/17/2025 | Approved | PAUL DAVIDSON |
| METHANE-Subgrade | 12/17/2025 | Approved | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 12/18/2025 | Conditional Approval | PAUL DAVIDSON |
| Special/Order Compliance | 1/15/2026 | Partial Inspection | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 1/20/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 1/28/2026 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 1/29/2026 | Not Ready for Inspection | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2026 | Partial Inspection | PAUL DAVIDSON |
| Footing/Foundation/Slab | 1/30/2026 | Partial Approval | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2026 | Not Ready for Inspection | PAUL DAVIDSON |
| Special/Order Compliance | 2/18/2026 | Not Ready for Inspection | DANIEL ARMENTA |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2026 | Partial Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 2/24/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 2/27/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Shotcrete | 2/27/2026 | Conditional Approval | PAUL DAVIDSON |
| Special/Order Compliance | 3/6/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 3/31/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 4/13/2026 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 4/13/2026 | Partial Approval | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2026 | Partial Approval | PAUL DAVIDSON |
| Deputy Wood Construction | 5/22/2026 | Conditional Approval | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2026 | Partial Approval | PAUL DAVIDSON |
| Deputy Wood Construction | 6/16/2026 | Conditional Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2026 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2026 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 7/10/2026 | No Access for Inspection | PAUL DAVIDSON |
| Drywall Nailing | 7/13/2026 | Partial Approval | PAUL DAVIDSON |