1532 W GAGE AVE 90047
Certificate Information: 1532 W GAGE AVE 90047
- Application / Permit
- 24010-10000-02066
- Plan Check / Job No.
- B24LA09183
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ADU ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
- Permit Issued
- Issued on 8/21/2024
- Issuing Office
- Metro
- Current Status
- Issued on 8/21/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | SUNMIN LEE |
| Corrections Issued | 5/17/2024 | SUNMIN LEE |
| Quality Review Completed | 5/22/2024 | KEN GILL |
| Building Plans Picked Up | 5/24/2024 | APPLICANT |
| Applicant returned to address corrections | 8/6/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 8/14/2024 | SUNMIN LEE |
| Plan Check Approved | 8/21/2024 | SUNMIN LEE |
| Issued | 8/21/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/24/2024 | DAVID LOPEZ |
| Construction within easement | Cleared | 7/27/2024 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 8/7/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2024 | JEANIE LAM |
| Sewer availability | Cleared | 8/8/2024 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moon,, Douglas Michael; Lic. No.: S6495 | 11881 FLICKER COVE CORONA, CA 92883 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/26/2024 | Corrections Issued | CRAIG DAVIS |
| Pre-Inspection | 8/26/2024 | Corrections Issued | CRAIG DAVIS |
| Sewer | 8/26/2024 | Corrections Issued | CRAIG DAVIS |
| Underground Mechanical | 8/26/2024 | Corrections Issued | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 9/24/2024 | No Access for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 9/24/2024 | No Access for Inspection | JOHN QUINTANILLA |
| Sewer | 9/24/2024 | No Access for Inspection | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 9/26/2024 | Partial Inspection | CRAIG DAVIS |
| Sewer | 9/26/2024 | Partial Approval | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 10/1/2024 | Approved | CRAIG DAVIS |
| Footing/Foundation/Slab | 10/1/2024 | Approved | CRAIG DAVIS |
| Sewer | 10/1/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Rough | 11/7/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2024 | Corrections Issued | CRAIG DAVIS |
| Gas Test | 11/7/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 11/7/2024 | Corrections Issued | CRAIG DAVIS |
| Wall Anchors | 11/7/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Wood Frame | 11/7/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 11/15/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 11/20/2024 | Corrections Issued | JOSE MACIAS |
| Underground Mechanical | 11/20/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 11/22/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 12/19/2024 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 12/19/2024 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 12/19/2024 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 2/24/2025 | Not Ready for Inspection | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Corrections Issued | BARRY HACHE |
| Green Building Rough | 2/24/2025 | Not Ready for Inspection | BARRY HACHE |
| Verify Sprinkler Sign Off | 2/24/2025 | Not Ready for Inspection | BARRY HACHE |
| Deputy Wood Construction | 2/26/2025 | Conditional Approval | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 3/13/2025 | Not Ready for Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 3/14/2025 | Approved | REGINA MENDEZ |
| Rough-Elec/Plmb/HVAC | 4/22/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 4/25/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 4/25/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 4/28/2025 | Corrections Issued | BARRY HACHE |
| Green Building Rough | 4/28/2025 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 4/28/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 5/6/2025 | Approved | BARRY HACHE |
| Insulation | 5/6/2025 | Approved | BARRY HACHE |
| Drywall Nailing | 5/29/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 7/24/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 7/25/2025 | Approved | BARRY HACHE |