4573 E YELLOWSTONE ST 90032

Certificate Information: 4573 E YELLOWSTONE ST 90032

Application / Permit
24010-10000-02009
Plan Check / Job No.
B24LA08934
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU including two bedrooms, 2 bathrooms, kitchen, dining and living room
Permit Issued
Issued on 4/2/2025
Issuing Office
Current Status
CofO Issued on 3/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2024 APPLICANT
Assigned to Plan Check Engineer 5/23/2024 JOE VO
Corrections Issued 5/26/2024 JOE VO
Quality Review Completed 6/7/2024 GARO TELMI
Plan Check Approved 3/25/2025 JOE VO
Issued 4/2/2025 APPLICANT
CofO in Progress 3/27/2026 LILIANA PORTILLO
Permit Finaled 3/28/2026 DEROLD HAUFF
CofO Issued 3/28/2026 DEROLD HAUFF
Permit Finaled 3/28/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/12/2024 JUSTIN BICOL
BHO/Hillside ordinance Cleared 6/12/2024 JUSTIN BICOL
BHO/Hillside ordinance Cleared 6/12/2024 JUSTIN BICOL
BHO/Hillside ordinance Cleared 6/12/2024 JUSTIN BICOL
BHO/Hillside ordinance Cleared 6/12/2024 JUSTIN BICOL
BHO/Hillside ordinance Cleared 6/12/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 6/13/2024 JUSTIN BICOL
Sewer availability Cleared 6/13/2024 JUSTIN BICOL
Low Impact Development (LID) Cleared 6/17/2024 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 6/21/2024 AMBER CAMPBELL
Construction near power lines Cleared 10/22/2024 TINA MIRANDA
Hydrant and Access approval Cleared 2/13/2025 KURT CORRAL
"D" conditions Cleared 3/13/2025 RUBEN VASQUEZ
"Q" conditions Cleared 3/13/2025 RUBEN VASQUEZ
Grading Pre-Inspection Cleared 3/25/2025 JONATHAN HOM

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/3/2025 Partial Inspection LILIANA PORTILLO
Footing/Foundation/Slab 8/6/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 8/6/2025 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/16/2025 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 9/23/2025 Not Ready for Inspection WILLIAM SIERRA
ELECTRICAL-Rough 9/23/2025 Approved WILLIAM SIERRA
HVAC-Rough 9/23/2025 Corrections Issued WILLIAM SIERRA
PLUMBING-Rough 9/23/2025 Corrections Issued WILLIAM SIERRA
Verify Sprinkler Sign Off 9/23/2025 Approved WILLIAM SIERRA
HVAC-Rough 9/26/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 9/26/2025 Approved LILIANA PORTILLO
Shower Pan 9/26/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 10/10/2025 Approved REGINA MENDEZ
Insulation 10/15/2025 Conditional Approval LILIANA PORTILLO
Drywall Nailing 10/21/2025 Conditional Approval ANTHONY RAMOS
BUILDING-Rough-Frame 12/17/2025 Approved LILIANA PORTILLO
Drywall Nailing 12/17/2025 Approved LILIANA PORTILLO
Footing/Foundation/Slab 12/17/2025 Approved LILIANA PORTILLO
Insulation 12/17/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 12/31/2025 Corrections Issued ALIZAH MAYAGOITIA
Sewer 12/31/2025 Approved ALIZAH MAYAGOITIA
Special/Order Compliance 1/14/2026 Partial Inspection LILIANA PORTILLO
Underground Mechanical 1/23/2026 Approved LILIANA PORTILLO
Final 2/4/2026 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/4/2026 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 2/4/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 2/4/2026 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 2/12/2026 Approved LILIANA PORTILLO
Final 2/12/2026 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 2/12/2026 Approved LILIANA PORTILLO
PLUMBING-Final 2/12/2026 Approved LILIANA PORTILLO
Service/Power Release 2/12/2026 Not Ready for Inspection LILIANA PORTILLO
Final 3/5/2026 Corrections Issued LILIANA PORTILLO
Service/Power Release 3/5/2026 Not Ready for Inspection LILIANA PORTILLO
Final 3/25/2026 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 3/25/2026 Approved LILIANA PORTILLO