8495-8503 W CRESCENT DR 90046
Certificate Information: 8495-8503 W CRESCENT DR 90046
- Application / Permit
- 24010-10000-02006
- Plan Check / Job No.
- B24LA08930
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION ADU OVER (E) CARPORT ATTACHED TO (E) SFD PER LAMC 12.22 A.33(c) AND (e) Fire sprinkler
- Permit Issued
- Issued on 12/6/2024
- Issuing Office
- Current Status
- Issued on 12/6/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | KHEDER ALRAZAA |
| Corrections Issued | 6/4/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 6/19/2024 | GARO TELMI |
| Applicant returned to address corrections | 10/24/2024 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 11/1/2024 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 11/14/2024 | KHEDER ALRAZAA |
| Plan Check Approved | 12/4/2024 | KHEDER ALRAZAA |
| Issued | 12/6/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/12/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 7/17/2024 | CELINA MORENO |
| Sewer availability | Cleared | 7/17/2024 | CELINA MORENO |
| Street Frontage | Cleared | 7/19/2024 | CELINA MORENO |
| GPI Written Notices | Cleared | 10/28/2024 | KHEDER ALRAZAA |
| Grading Pre-Inspection | Cleared | 10/28/2024 | KHEDER ALRAZAA |
Contact Information
| Architect | Kazanjian,, Natalia Noyemi; Lic. No.: NA34684 | , |
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/8/2025 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/17/2025 | Corrections Issued | ROY SPAULDING |
| Pre-Inspection | 4/21/2025 | Not Ready for Inspection | ROY SPAULDING |
| Pre-Inspection | 4/23/2025 | Partial Approval | ROY SPAULDING |
| Green Building Rough | 5/2/2025 | Not Ready for Inspection | ROY SPAULDING |
| Footing/Foundation/Slab | 5/23/2025 | Partial Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 6/10/2025 | Conditional Approval | JOSH MEISTER |
| Deputy Drilled-In Anchors | 6/16/2025 | Conditional Approval | JOSH MEISTER |
| Footing/Foundation/Slab | 6/17/2025 | Partial Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 6/30/2025 | Partial Approval | BRENDAN MORELLI |
| Deputy Steel/Welding | 7/1/2025 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Rough | 7/14/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 7/14/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 8/26/2025 | Partial Inspection | SCOTT FINNILA |
| Deputy Wood Construction | 8/26/2025 | Conditional Approval | JOSH MEISTER |
| Green Building Rough | 8/26/2025 | Partial Inspection | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 8/26/2025 | Partial Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2025 | Partial Approval | ROY SPAULDING |
| BUILDING-Rough-Frame | 1/9/2026 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 1/9/2026 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 1/9/2026 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Rough | 1/9/2026 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 1/9/2026 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 1/9/2026 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 1/16/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Rough | 1/16/2026 | Approved | DAVID WILLIAMS |
| Rough-Elec/Plmb/HVAC | 1/16/2026 | Corrections Issued | DAVID WILLIAMS |
| Verify Sprinkler Sign Off | 1/16/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 3/23/2026 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Rough | 3/23/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 3/23/2026 | Partial Approval | DAVID WILLIAMS |
| PLUMBING-Rough | 3/23/2026 | Approved | DAVID WILLIAMS |
| Rough-Elec/Plmb/HVAC | 3/23/2026 | Approved | DAVID WILLIAMS |
| Underground Mechanical | 3/23/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Verify Sprinkler Sign Off | 3/23/2026 | Approved | DAVID WILLIAMS |
| Insulation | 4/15/2026 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 5/7/2026 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 6/4/2026 | Approved | BRENDAN MORELLI |