2522 1/2 W ELSINORE ST 90026
Certificate Information: 2522 1/2 W ELSINORE ST 90026
- Application / Permit
- 24010-10000-02003
- Plan Check / Job No.
- B24LA08923
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW ONE STORY ADU WITH NEW ATTACHED TWO CAR GARAGE PER ENGINEER DESIGN (1,200 SF max per Ordinance , LAMC 12.22 A.33(c) AND (d))
- Permit Issued
- Issued on 12/6/2024
- Issuing Office
- Current Status
- CofO Issued on 10/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/17/2024 | NGHI SU |
| Corrections Issued | 5/18/2024 | NGHI SU |
| Applicant returned to address corrections | 9/25/2024 | AUNG SOE |
| Plan Check Approved | 9/26/2024 | AUNG SOE |
| Issued | 12/6/2024 | APPLICANT |
| CofO in Progress | 10/10/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 10/11/2025 | DEROLD HAUFF |
| Permit Finaled | 10/11/2025 | DEROLD HAUFF |
| CofO Issued | 10/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 5/18/2024 | NGHI SU |
| Grading Pre-Inspection | Cleared | 5/18/2024 | NGHI SU |
| Roof/Waste drainage to street | Cleared | 5/20/2024 | ANTHONY TRAN |
| Address approval | Cleared | 8/14/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 8/14/2024 | AMBER CAMPBELL |
| Hydrant and Access approval | Cleared | 9/9/2024 | RUEL COLE |
Contact Information
| Contractor | Neeraj Mittal; Lic. No.: 1127454-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/11/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Inspection | 12/11/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 12/17/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/17/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| METHANE-Barrier | 12/17/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| METHANE-Subgrade | 12/17/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Methane Barrier | 12/18/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 12/20/2024 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 12/20/2024 | Approved | OSVALDO PARAMO |
| METHANE-Barrier | 12/20/2024 | Approved | OSVALDO PARAMO |
| METHANE-Subgrade | 12/20/2024 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 1/10/2025 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/10/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/24/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 3/24/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| METHANE-Rough | 3/24/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/24/2025 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 3/24/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/2/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 4/2/2025 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 4/2/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/2/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/8/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/8/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/11/2025 | Partial Approval | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 4/15/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 4/15/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/21/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 4/21/2025 | Approved | HAMIK HARTOUNIAN |
| Insulation | 4/21/2025 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 4/30/2025 | Approved | ALEX COLIN |
| Shower Pan | 4/30/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 5/7/2025 | Approved | REGINA MENDEZ |
| Service/Power Release | 9/5/2025 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 9/19/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 9/19/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 9/19/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Final | 9/19/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Final | 9/19/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 9/19/2025 | SGSOV No Gas | HAMIK HARTOUNIAN |
| Service/Power Release | 9/19/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/19/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 10/6/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 10/6/2025 | Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 10/6/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 10/10/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Service/Power Release | 10/10/2025 | Approved | HAMIK HARTOUNIAN |