2111 S BEVERLY DR 90034
Certificate Information: 2111 S BEVERLY DR 90034
- Application / Permit
- 24010-10000-02002
- Plan Check / Job No.
- B24LA08912
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION TO (E) SINGLE FAMILY DWELLING TO CREATE 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 10/22/2024
- Issuing Office
- Current Status
- CofO Issued on 5/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | DANIEL YIP |
| Corrections Issued | 5/20/2024 | DANIEL YIP |
| Quality Review Completed | 5/22/2024 | KEN GILL |
| Building Plans Picked Up | 5/22/2024 | APPLICANT |
| Plan Check Approved | 10/11/2024 | DANIEL YIP |
| Plan Check Approved | 10/22/2024 | DANIEL YIP |
| Issued | 10/22/2024 | APPLICANT |
| CofO in Progress | 5/8/2026 | ASHLEY THOMPSON |
| Permit Finaled | 5/11/2026 | RICHARD STEINBACH |
| CofO Issued | 5/11/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/11/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 5/28/2024 | DARIN LAM |
| Construction near power lines | Cleared | 6/14/2024 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 7/3/2024 | DARIN LAM |
| Hydrant and Access approval | Cleared | 7/5/2024 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2024 | DARIN LAM |
| Sewer availability | Cleared | 7/6/2024 | DARIN LAM |
| Trees in Parkway | Cleared | 9/11/2024 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 9/25/2024 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 9/25/2024 | DANIEL YIP |
Contact Information
| Architect | Leishman,, Thomas Edward; Lic. No.: C15059 | 28100 RIDGEFERN COURT RANCHO PALOS VERDES, CA 90275 |
| Contractor | David Elliot Builders Inc; Lic. No.: 1021000-B | 5979 W 3RD ST SUITE #203 LOS ANGELES, CA 90036 |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/27/2024 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 12/5/2024 | Conditional Approval | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 12/6/2024 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 12/6/2024 | Partial Approval | MEL KHACHATOURIAN |
| METHANE-Barrier | 12/6/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Subgrade | 12/6/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 12/6/2024 | Partial Approval | MEL KHACHATOURIAN |
| METHANE-Subgrade | 12/11/2024 | Approved | ASHLEY THOMPSON |
| Underground Mechanical | 12/11/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 12/19/2024 | Approved | ARAM AVEDISIAN |
| METHANE-Barrier | 12/19/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/22/2025 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Conditional Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2025 | Partial Approval | MEL KHACHATOURIAN |
| Underground Mechanical | 2/28/2025 | Approved | ASHLEY THOMPSON |
| Deputy Wood Construction | 4/2/2025 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 6/24/2025 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 6/24/2025 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 6/25/2025 | Conditional Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 6/25/2025 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 6/26/2025 | Approved | ASHLEY THOMPSON |
| Final | 6/26/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2025 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 6/26/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Rough | 6/26/2025 | Approved | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 6/26/2025 | Approved | ASHLEY THOMPSON |
| Insulation | 7/24/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 7/24/2025 | Partial Approval | ASHLEY THOMPSON |
| Shower Pan | 7/24/2025 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 8/5/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 8/5/2025 | Corrections Issued | ASHLEY THOMPSON |
| Gas Test | 3/24/2026 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 4/29/2026 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 4/29/2026 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 4/30/2026 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 4/30/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 4/30/2026 | Approved | ASHLEY THOMPSON |
| Final | 5/5/2026 | OK to Issue CofO | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 5/5/2026 | Approved | ASHLEY THOMPSON |
| Green Building Final | 5/5/2026 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 5/5/2026 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 5/5/2026 | SGSOV Approved | ASHLEY THOMPSON |
| Service/Power Release | 5/5/2026 | Approved | ASHLEY THOMPSON |
| Smoke Detectors | 5/5/2026 | Approved | ASHLEY THOMPSON |