5204 1/2 E BALTIMORE ST 90042

Certificate Information: 5204 1/2 E BALTIMORE ST 90042

Application / Permit
24010-10000-01989
Plan Check / Job No.
B24LA08887
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: New detached 1-Story ADU with roof deck PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 11/7/2024
Issuing Office
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2024 APPLICANT
Assigned to Plan Check Engineer 5/23/2024 KHEDER ALRAZAA
Corrections Issued 6/7/2024 KHEDER ALRAZAA
Quality Review Completed 6/19/2024 GARO TELMI
Applicant returned to address corrections 9/4/2024 KHEDER ALRAZAA
Plan Check Approved 10/18/2024 KHEDER ALRAZAA
Issued 11/7/2024 APPLICANT
CofO in Progress 5/27/2026 NICHOLAS LOPEZ
CofO Issued 5/28/2026 DEROLD HAUFF
Permit Finaled 5/28/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/8/2024 CELINA MORENO
Roof/Waste drainage to street Cleared 6/8/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/11/2024 CELINA MORENO
Sewer availability Cleared 6/11/2024 CELINA MORENO
Street Frontage Cleared 6/11/2024 CELINA MORENO
Hydrant and Access approval Cleared 8/8/2024 GILBERT URREA
GPI Written Notices Cleared 10/18/2024 KHEDER ALRAZAA
Grading Pre-Inspection Cleared 10/18/2024 KHEDER ALRAZAA

Contact Information

Contractor Owner-Builder       ,
Engineer Daugherty,, Daniel Thomas; Lic. No.: C76588 31129 VIA COLINAS STE 707      WESTLAKE VILLAGE, CA 91362
Engineer Meleika,, Samuel H; Lic. No.: C86049 5225 CANYON CREST DR. STE 71 #137   RIVERSIDE    RIVERSIDE, CA 92507
Engineer Sunna,, Nadim; Lic. No.: C84197 27035 MARISCAL LN      MISSION VIEJO, CA 92691
Geologist Daugherty,, Daniel Thomas; Lic. No.: EG2569 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/24/2025 Partial Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 2/24/2025 Partial Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 4/4/2025 Approved NICHOLAS LOPEZ
PLUMBING-Rough 4/4/2025 Partial Approval NICHOLAS LOPEZ
Deputy Wood Construction 5/29/2025 Conditional Approval NICHOLAS LOPEZ
Rough-Elec/Plmb/HVAC 7/14/2025 Corrections Issued NICHOLAS LOPEZ
BUILDING-Rough-Frame 7/16/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 7/16/2025 Approved NICHOLAS LOPEZ
Green Building Rough 7/16/2025 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Rough 7/16/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Rough 7/16/2025 Approved NICHOLAS LOPEZ
Structural Steel Frame 7/16/2025 Conditional Approval NICHOLAS LOPEZ
Verify Sprinkler Sign Off 7/16/2025 Approved NICHOLAS LOPEZ
Wood Frame 7/16/2025 Not Ready for Inspection NICHOLAS LOPEZ
BUILDING-Rough-Frame 7/22/2025 Approved NICHOLAS LOPEZ
Green Building Rough 7/22/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 7/22/2025 Conditional Approval NICHOLAS LOPEZ
Insulation 7/28/2025 Conditional Approval NICHOLAS LOPEZ
Drywall Nailing 7/31/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 8/4/2025 Approved NICHOLAS LOPEZ
Shower Pan 8/4/2025 Approved NICHOLAS LOPEZ
Green Building Final 8/19/2025 Not Ready for Inspection NICHOLAS LOPEZ
Pre-Inspection 8/19/2025 Partial Inspection NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 8/19/2025 SGSOV No Gas NICHOLAS LOPEZ
Service/Power Release 8/19/2025 Not Ready for Inspection NICHOLAS LOPEZ
Smoke Detectors 8/19/2025 Not Ready for Inspection NICHOLAS LOPEZ
Final 9/9/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 9/9/2025 Not Ready for Inspection NICHOLAS LOPEZ
Service/Power Release 9/9/2025 Not Ready for Inspection NICHOLAS LOPEZ
Smoke Detectors 9/9/2025 Not Ready for Inspection NICHOLAS LOPEZ
Pre-Inspection 1/26/2026 Partial Inspection NICHOLAS LOPEZ
ELECTRICAL-Rough 3/31/2026 Approved NICHOLAS LOPEZ
Pre-Inspection 4/6/2026 Partial Inspection NICHOLAS LOPEZ
ELECTRICAL-Final 5/21/2026 Corrections Issued NICHOLAS LOPEZ
Final 5/21/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Final 5/21/2026 Corrections Issued NICHOLAS LOPEZ
HVAC-Final 5/21/2026 Approved NICHOLAS LOPEZ
PLUMBING-Final 5/21/2026 Corrections Issued NICHOLAS LOPEZ
Service/Power Release 5/21/2026 Not Ready for Inspection NICHOLAS LOPEZ
Smoke Detectors 5/21/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 5/26/2026 Approved NICHOLAS LOPEZ
Final 5/26/2026 OK to Issue CofO NICHOLAS LOPEZ
Green Building Final 5/26/2026 Approved NICHOLAS LOPEZ
HVAC-Final 5/26/2026 Approved NICHOLAS LOPEZ
PLUMBING-Final 5/26/2026 Approved NICHOLAS LOPEZ
Service/Power Release 5/26/2026 Approved NICHOLAS LOPEZ