14415 W MARTHA ST 91401

Certificate Information: 14415 W MARTHA ST 91401

Application / Permit
24010-10000-01971
Plan Check / Job No.
B24LA08806
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan New Detached, 2-Story ADU Per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 12/9/2024
Issuing Office
Current Status
CofO Issued on 1/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2024 APPLICANT
Assigned to Plan Check Engineer 5/23/2024 MAHNAZ NOURHASHEMI
Corrections Issued 5/30/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 6/5/2024 TU HUA
Applicant returned to address corrections 7/7/2024 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 7/11/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 11/1/2024 MAHNAZ NOURHASHEMI
No Progress 11/1/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 11/1/2024 MAHNAZ NOURHASHEMI
Issued 12/9/2024 APPLICANT
CofO in Progress 12/26/2025 RYAN SALAZAR
Permit Finaled 1/8/2026 RUBEN SALAS
CofO Issued 1/8/2026 RUBEN SALAS
Permit Finaled 1/8/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/9/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 7/15/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/15/2024 LEE GUILBEAUX
Sewer availability Cleared 7/15/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 7/15/2024 LEE GUILBEAUX
Construction near power lines Cleared 10/24/2024 TINA MIRANDA
Construction within easement Cleared 10/24/2024 TINA MIRANDA

Contact Information

Contractor Jas General Construction; Lic. No.: 1026356-B       ,
Engineer Black,, Ian Robert; Lic. No.: S5505 19401 OLANA LN      HUNTINGTON BEACH, CA 92646

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/15/2025 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 1/15/2025 Partial Approval RYAN SALAZAR
PLUMBING-Rough 1/15/2025 Partial Approval RYAN SALAZAR
Deputy Wood Construction 3/14/2025 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 3/19/2025 Partial Approval RYAN SALAZAR
PLUMBING-Rough 3/19/2025 Approved RYAN SALAZAR
Sewer 4/3/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 4/22/2025 Corrections Issued RYAN SALAZAR
ELECTRICAL-Rough 4/22/2025 Approved RYAN SALAZAR
Green Building Rough 4/22/2025 Approved RYAN SALAZAR
HVAC-Rough 4/22/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/22/2025 Partial Approval RYAN SALAZAR
PLUMBING-Rough 4/22/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 4/22/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 4/30/2025 Corrections Issued RYAN SALAZAR
Insulation 4/30/2025 Corrections Issued RYAN SALAZAR
Interior/Exterior Lathing 4/30/2025 Approved RYAN SALAZAR
Drywall Nailing 5/5/2025 Approved RYAN SALAZAR
Underground Mechanical 6/12/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 9/16/2025 Approved RYAN SALAZAR
Final 9/16/2025 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 9/16/2025 Approved RYAN SALAZAR
Green Building Final 9/16/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 9/16/2025 SGSOV Not Required RYAN SALAZAR
Service/Power Release 9/16/2025 Approved RYAN SALAZAR
Smoke Detectors 9/16/2025 Approved RYAN SALAZAR
Final 12/29/2025 OK to Issue CofO RYAN SALAZAR