2237 S MANSFIELD AVE 90016

Certificate Information: 2237 S MANSFIELD AVE 90016

Application / Permit
24010-10000-01920
Plan Check / Job No.
B24LA08551
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU 799 SF PER STATE LAW. WORK PER PER WFPP.
Permit Issued
Issued on 6/4/2024
Issuing Office
Current Status
CofO Issued on 11/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 ADAM HEGAZI
Corrections Issued 5/11/2024 ADAM HEGAZI
Building Plans Picked Up 5/14/2024 APPLICANT
Applicant returned to address corrections 5/24/2024 HUAN LE
Plan Check Approved 6/4/2024 HUAN LE
Issued 6/4/2024 APPLICANT
CofO in Progress 11/13/2025 JUSTIN HAWLEY
Permit Finaled 11/16/2025 DEROLD HAUFF
CofO Issued 11/16/2025 DEROLD HAUFF
Permit Finaled 11/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/24/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 5/24/2024 JESSICA OPINION
Roof/Waste drainage to street Cleared 5/24/2024 JESSICA OPINION
Sewer availability Cleared 5/24/2024 JESSICA OPINION

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/6/2024 Not Ready for Inspection AMIR NAZARIAN
Excavation/Setback/Form/Re-Bar 9/4/2024 Not Ready for Inspection JUSTIN HAWLEY
Underground Mechanical 9/4/2024 Partial Approval JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 9/12/2024 Approved JUSTIN HAWLEY
Underground Mechanical 9/12/2024 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 10/16/2024 Not Ready for Inspection JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Partial Approval JUSTIN HAWLEY
Footing/Foundation/Slab 10/16/2024 Approved JUSTIN HAWLEY
Green Building Rough 10/16/2024 Not Ready for Inspection JUSTIN HAWLEY
MERV13>=Rough 10/16/2024 Approved JUSTIN HAWLEY
Deputy Wood Construction 10/17/2024 Conditional Approval NICHOLAS LOPEZ
ELECTRICAL-Rough 10/29/2024 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Approved BRENDAN MORELLI
HVAC-Rough 10/29/2024 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 10/29/2024 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 11/6/2024 Corrections Issued JOHN QUINTANILLA
Green Building Rough 11/6/2024 Corrections Issued JOHN QUINTANILLA
Interior/Exterior Lathing 11/6/2024 Approved JOHN QUINTANILLA
PLUMBING-Rough 11/6/2024 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 11/8/2024 Partial Inspection ANTHONY RAMOS
Insulation 11/8/2024 Partial Approval ANTHONY RAMOS
Drywall Nailing 11/19/2024 Approved JOHN QUINTANILLA
Green Building Rough 11/19/2024 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 11/26/2024 Approved ANTHONY RAMOS
Underground Mechanical 12/10/2024 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 4/23/2025 Approved JOSE MACIAS
Final 4/23/2025 Corrections Issued JOSE MACIAS
Green Building Final 4/23/2025 Approved JOSE MACIAS
MERV13>=Final 4/23/2025 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 4/23/2025 SGSOV Approved JOSE MACIAS
Service/Power Release 4/23/2025 Not Ready for Inspection JOSE MACIAS
Smoke Detectors 4/23/2025 Approved JOSE MACIAS
Final 5/16/2025 Not Ready for Inspection ARTHUR NEGRETE
Service/Power Release 5/16/2025 Not Ready for Inspection ARTHUR NEGRETE
Service/Power Release 5/30/2025 Approved ARTHUR NEGRETE
Final 8/11/2025 Corrections Issued JUSTIN HAWLEY
HVAC-Final 8/11/2025 Approved JUSTIN HAWLEY
Final 11/8/2025 Off-Hour Fees Due
Final 11/13/2025 OK to Issue CofO JUSTIN HAWLEY