8333 N QUARTZ AVE 91306

Certificate Information: 8333 N QUARTZ AVE 91306

Application / Permit
24010-10000-01913
Plan Check / Job No.
B24LA08519
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED ACCESSORY DWELLING UNIT WITH ATTACHED GARAGE PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 11/7/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2024 APPLICANT
Assigned to Plan Check Engineer 5/16/2024 SINA KHOSRAVI
Corrections Issued 5/21/2024 SINA KHOSRAVI
Quality Review Completed 5/24/2024 KEN GILL
Building Plans Picked Up 5/29/2024 APPLICANT
Applicant returned to address corrections 6/18/2024 SINA KHOSRAVI
Plan Check Approved 10/30/2024 SINA KHOSRAVI
Issued 11/7/2024 APPLICANT
CofO in Progress 5/13/2026 JEFFREY HARTLINE
Permit Finaled 5/26/2026 JOHN JANSON
CofO Issued 5/26/2026 JOHN JANSON
Permit Finaled 5/26/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/3/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/3/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/4/2024 CARLOS AGUILERA
Sewer availability Cleared 6/4/2024 CARLOS AGUILERA
Construction near power lines Cleared 10/21/2024 TINA MIRANDA
Construction within easement Cleared 10/21/2024 TINA MIRANDA
Miscellaneous Cleared 10/30/2024 SINA KHOSRAVI

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/11/2025 Partial Approval JEFFREY HARTLINE
Footing/Foundation/Slab 3/27/2025 Corrections Issued JEFFREY HARTLINE
Footing/Foundation/Slab 4/7/2025 Conditional Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/6/2025 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Corrections Issued JEFFREY HARTLINE
BUILDING-Rough-Frame 6/25/2025 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Rough 6/25/2025 Approved JEFFREY HARTLINE
Green Building Rough 6/25/2025 Approved JEFFREY HARTLINE
HVAC-Rough 6/25/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 6/25/2025 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 6/25/2025 Approved JEFFREY HARTLINE
Sewer 6/25/2025 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 6/25/2025 Approved JEFFREY HARTLINE
Insulation 7/8/2025 Conditional Approval CHRIS CHRISTENSEN
Drywall Nailing 7/14/2025 Approved JEFFREY HARTLINE
Underground Mechanical 7/14/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 1/14/2026 Approved JEFFREY HARTLINE
Final 1/14/2026 Corrections Issued JEFFREY HARTLINE
Footing/Foundation/Slab 1/14/2026 Approved JEFFREY HARTLINE
Green Building Final 1/14/2026 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 1/14/2026 SGSOV Not Ready JEFFREY HARTLINE
Service/Power Release 1/14/2026 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 1/14/2026 Approved JEFFREY HARTLINE
Final 4/15/2026 Corrections Issued JEFFREY HARTLINE
Green Building Final 4/15/2026 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 4/15/2026 SGSOV Not Required JEFFREY HARTLINE
Service/Power Release 4/15/2026 Not Ready for Inspection JEFFREY HARTLINE
Final 4/29/2026 OK to Issue CofO JEFFREY HARTLINE
Service/Power Release 4/29/2026 Approved JEFFREY HARTLINE