902 W 30TH ST 90007
Certificate Information: 902 W 30TH ST 90007
- Application / Permit
- 24010-10000-01880
- Plan Check / Job No.
- B24LA08362
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- Foundation only permit for: 23010-20000- 02425- WOMEN'S SOCCER AND LACROSSE STADIUM TYPE II-B. PAVILION BUILDING AND PRESS BOX WITH PUBLIC AREA BENEATH SEATING
- Permit Issued
- Issued on 5/31/2024
- Issuing Office
- Current Status
- Permit Finaled on 6/25/2025
- Certificate of Occupancy
- TCO Issued More Information
Permit Application Status History
| Submitted | 5/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2024 | HERNAN ARREOLA |
| Plan Check Approved | 5/31/2024 | HERNAN ARREOLA |
| Issued | 5/31/2024 | APPLICANT |
| Permit Finaled | 6/25/2025 | JAMES POWERS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2024 | DAVID LOPEZ |
| Highway dedication | Cleared | 5/6/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 5/6/2024 | DAVID LOPEZ |
| Work Adjacent to Public Way | Cleared | 5/6/2024 | LARRY LEE |
| Green Code | Cleared | 5/7/2024 | AARON COSTA |
| Driveway location | Cleared | 5/15/2024 | JOSE CARDENAS |
| Fire Marshal Fire Life Safety | Cleared | 5/15/2024 | DOMINIQUE MEDINA |
| Redevelopment Project Area | Cleared | 5/16/2024 | ELIZABETH GALLARDO |
| CPC | Cleared | 5/30/2024 | DAVID URITA |
Contact Information
| Architect | Murphy,, David Merle; Lic. No.: C32028 | 1801 MCGEE STREET SUITE 200 KANSAS CITY, MO 64108 |
| Contractor | Clark Construction Group California Lp; Lic. No.: 839892-A | 7900 WESTPARK DRIVE SUITE T300 MCLEAN, VA 22102 |
| Engineer | Hill,, Edward Foster; Lic. No.: GE2126 | 27865 AMBERWOOD LANE VALENCIA, CA 91354 |
| Engineer | Treece,, Robert; Lic. No.: S4355 | 8107 NE 76TH TERRACE KANSAS CITY, MO 64158 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/4/2024 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 6/7/2024 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 6/13/2024 | Partial Approval | JAMES POWERS |
| METHANE-Barrier | 6/13/2024 | Partial Approval | JAMES POWERS |
| METHANE-Subgrade | 6/13/2024 | Not Ready for Inspection | JAMES POWERS |
| Piling/Pier/Caisson | 6/13/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 6/14/2024 | Conditional Approval | LARRY ARNICK |
| Excavation/Setback/Form/Re-Bar | 6/14/2024 | Conditional Approval | LARRY ARNICK |
| Excavation/Setback/Form/Re-Bar | 6/25/2024 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 6/26/2024 | Partial Approval | JAMES POWERS |
| METHANE-Barrier | 6/26/2024 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Subgrade | 6/26/2024 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Concrete | 6/27/2024 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 7/2/2024 | Partial Approval | JAMES POWERS |
| Deputy Methane Barrier | 7/9/2024 | Partial Approval | JAMES POWERS |
| Deputy Methane Barrier | 7/25/2024 | Partial Approval | JAMES POWERS |
| Deputy Methane Barrier | 7/31/2024 | Partial Approval | JAMES POWERS |
| Deputy Methane Barrier | 8/1/2024 | Partial Approval | ALFREDO LOPEZ |
| Deputy Methane Barrier | 8/2/2024 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 9/26/2024 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 9/27/2024 | Partial Approval | JAMES POWERS |
| METHANE-Barrier | 1/14/2025 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Barrier | 1/15/2025 | Not Ready for Inspection | JAMES POWERS |