902 W 30TH ST 90007

Certificate Information: 902 W 30TH ST 90007

Application / Permit
24010-10000-01880
Plan Check / Job No.
B24LA08362
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
Foundation only permit for: 23010-20000- 02425- WOMEN'S SOCCER AND LACROSSE STADIUM TYPE II-B. PAVILION BUILDING AND PRESS BOX WITH PUBLIC AREA BENEATH SEATING
Permit Issued
Issued on 5/31/2024
Issuing Office
Current Status
Permit Finaled on 6/25/2025
Certificate of Occupancy
TCO Issued More Information

Permit Application Status History

Submitted 5/16/2024 APPLICANT
Assigned to Plan Check Engineer 5/20/2024 HERNAN ARREOLA
Plan Check Approved 5/31/2024 HERNAN ARREOLA
Issued 5/31/2024 APPLICANT
Permit Finaled 6/25/2025 JAMES POWERS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/6/2024 DAVID LOPEZ
Highway dedication Cleared 5/6/2024 DAVID LOPEZ
Sewer availability Cleared 5/6/2024 DAVID LOPEZ
Work Adjacent to Public Way Cleared 5/6/2024 LARRY LEE
Green Code Cleared 5/7/2024 AARON COSTA
Driveway location Cleared 5/15/2024 JOSE CARDENAS
Fire Marshal Fire Life Safety Cleared 5/15/2024 DOMINIQUE MEDINA
Redevelopment Project Area Cleared 5/16/2024 ELIZABETH GALLARDO
CPC Cleared 5/30/2024 DAVID URITA

Contact Information

Architect Murphy,, David Merle; Lic. No.: C32028 1801 MCGEE STREET SUITE 200      KANSAS CITY, MO 64108
Contractor Clark Construction Group California Lp; Lic. No.: 839892-A 7900 WESTPARK DRIVE SUITE T300      MCLEAN, VA 22102
Engineer Hill,, Edward Foster; Lic. No.: GE2126 27865 AMBERWOOD LANE      VALENCIA, CA 91354
Engineer Treece,, Robert; Lic. No.: S4355 8107 NE 76TH TERRACE      KANSAS CITY, MO 64158

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/4/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/7/2024 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 6/13/2024 Partial Approval JAMES POWERS
METHANE-Barrier 6/13/2024 Partial Approval JAMES POWERS
METHANE-Subgrade 6/13/2024 Not Ready for Inspection JAMES POWERS
Piling/Pier/Caisson 6/13/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/14/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 6/14/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 6/25/2024 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 6/26/2024 Partial Approval JAMES POWERS
METHANE-Barrier 6/26/2024 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 6/26/2024 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/27/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/2/2024 Partial Approval JAMES POWERS
Deputy Methane Barrier 7/9/2024 Partial Approval JAMES POWERS
Deputy Methane Barrier 7/25/2024 Partial Approval JAMES POWERS
Deputy Methane Barrier 7/31/2024 Partial Approval JAMES POWERS
Deputy Methane Barrier 8/1/2024 Partial Approval ALFREDO LOPEZ
Deputy Methane Barrier 8/2/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/26/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/27/2024 Partial Approval JAMES POWERS
METHANE-Barrier 1/14/2025 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 1/15/2025 Not Ready for Inspection JAMES POWERS