13536 W MORRISON ST 91423

Certificate Information: 13536 W MORRISON ST 91423

Application / Permit
24010-10000-01835
Plan Check / Job No.
B24LA08201
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 55'4" X 45' TWO STORY SFD WITH ATTACHED TWO CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQURIED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 7/2/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 RARES BODEA
Corrections Issued 5/16/2024 RARES BODEA
Quality Review Completed 5/17/2024 STEVEN KIM
Building Plans Picked Up 5/17/2024 APPLICANT
Plan Check Approved 7/2/2024 RARES BODEA
Issued 7/2/2024 APPLICANT
CofO in Progress 4/16/2025 JUAN VALENZUELA
CofO Issued 4/16/2025 RUBEN SALAS
Permit Finaled 4/16/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 5/17/2024 SARAH YOUSSEF
Address approval Cleared 5/20/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/20/2024 LEE GUILBEAUX
Permit Cleared 5/20/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/20/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/20/2024 LEE GUILBEAUX
Sewer availability Cleared 5/21/2024 LEE GUILBEAUX
ZI Cleared 6/12/2024 JACQUELINE TORRES
Trees in Parkway Cleared 6/18/2024 ADALBERTO VERA
Hydrant and Access approval Cleared 6/29/2024 RUEL COLE

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

DANIEL ORRANTE, (818) 374-1157 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/24/2024 Partial Approval VINCENT HANLEY
Sewer 7/24/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 7/29/2024 Approved MISAEL ESPARZA
Deputy Reinf. Concrete 7/31/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 8/9/2024 Partial Approval MISAEL ESPARZA
Deputy Wood Construction 8/19/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/23/2024 Corrections Issued MISAEL ESPARZA
HVAC-Rough 9/3/2024 Corrections Issued MISAEL ESPARZA
HVAC-Rough 9/5/2024 Approved MISAEL ESPARZA
PLUMBING-Rough 9/11/2024 Approved MISAEL ESPARZA
ELECTRICAL-Rough 9/23/2024 Corrections Issued MISAEL ESPARZA
Shower Pan 9/23/2024 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 9/25/2024 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 9/25/2024 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 9/25/2024 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 9/25/2024 Approved MISAEL ESPARZA
ELECTRICAL-Rough 9/26/2024 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 9/30/2024 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 9/30/2024 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 10/2/2024 Conditional Approval MISAEL ESPARZA
Shower Pan 10/2/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 10/4/2024 Conditional Approval MISAEL ESPARZA
Interior/Exterior Lathing 10/10/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/15/2024 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 10/18/2024 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 10/22/2024 Corrections Issued MISAEL ESPARZA
Green Building Rough 10/22/2024 Approved MISAEL ESPARZA
Insulation 10/22/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 11/6/2024 Conditional Approval MISAEL ESPARZA
Insulation 11/8/2024 Approved MISAEL ESPARZA
Drywall Nailing 11/13/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/13/2024 Approved MISAEL ESPARZA
HVAC-Final 2/26/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 2/28/2025 Corrections Issued MISAEL ESPARZA
Special/Order Compliance 3/10/2025 Partial Inspection JUAN VALENZUELA
ELECTRICAL-Final 3/19/2025 Approved JUAN VALENZUELA
HVAC-Final 3/19/2025 Approved JUAN VALENZUELA
PLUMBING-Final 3/26/2025 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 4/7/2025 Approved JUAN VALENZUELA
Final 4/7/2025 OK to Issue CofO JUAN VALENZUELA
Green Building Final 4/7/2025 Approved JUAN VALENZUELA
PLUMBING-Final 4/7/2025 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 4/7/2025 SGSOV Not Required JUAN VALENZUELA
Service/Power Release 4/7/2025 Approved JUAN VALENZUELA
Smoke Detectors 4/7/2025 Approved JUAN VALENZUELA