4926 E YORK BLVD 90042
Certificate Information: 4926 E YORK BLVD 90042
- Application / Permit
- 24010-10000-01827
- Plan Check / Job No.
- B24LA08162
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: (N) 1 STORY DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(a)(2), ALL WORK PER ENG.
- Permit Issued
- Issued on 3/20/2025
- Issuing Office
- Current Status
- CofO Issued on 2/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2024 | MOHAMMAD ESMAILI |
| Corrections Issued | 5/26/2024 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 8/16/2024 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 2/7/2025 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 2/13/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 3/1/2025 | LUISANGEL VALENZUELA |
| Issued | 3/20/2025 | APPLICANT |
| CofO in Progress | 2/20/2026 | DAVID WILLIAMS |
| Permit Finaled | 2/22/2026 | DEROLD HAUFF |
| CofO Issued | 2/22/2026 | DEROLD HAUFF |
| Permit Finaled | 2/22/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/30/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 10/30/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 10/30/2024 | DAVID LOPEZ |
| "Q" conditions | Cleared | 10/31/2024 | DANIEL CORONADO |
| Construction near power lines | Cleared | 1/25/2025 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 2/21/2025 | LANNY MERRICK |
Contact Information
| Contractor | J Z J B Cnst Inv; Lic. No.: 1013600-B | 345 W LORAINE ST 3 GLENDALE, CA 91202 |
| Engineer | Ramos,, Victor; Lic. No.: C86568 | 4823 ALMAGUER AVE GUADALUPE, CA 93434 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/30/2025 | Approved | DAVID WILLIAMS |
| Excavation/Setback/Form/Re-Bar | 5/20/2025 | Approved | DAVID WILLIAMS |
| Footing/Foundation/Slab | 5/20/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Rough | 6/18/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 6/18/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 6/18/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 7/14/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 7/14/2025 | Approved | REGINA MENDEZ |
| Insulation | 7/17/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/21/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 7/21/2025 | Approved | DAVID WILLIAMS |
| Insulation | 7/21/2025 | Approved | DAVID WILLIAMS |
| Verify Sprinkler Sign Off | 7/21/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 7/30/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 8/7/2025 | Approved | GEM DE OCAMPO |
| Sewer | 10/29/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Underground Mechanical | 10/29/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Sewer | 10/31/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Sewer | 11/6/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Final | 2/6/2026 | Approved | DAVID WILLIAMS |
| Final | 2/6/2026 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 2/6/2026 | Approved | DAVID WILLIAMS |
| HVAC-Final | 2/6/2026 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 2/6/2026 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 2/6/2026 | SGSOV No Gas | DAVID WILLIAMS |
| Service/Power Release | 2/6/2026 | Not Required | DAVID WILLIAMS |
| Smoke Detectors | 2/6/2026 | Approved | DAVID WILLIAMS |
| Final | 2/13/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Special/Order Compliance | 2/18/2026 | Approved | DAVID WILLIAMS |
| Final | 2/20/2026 | OK to Issue CofO | DAVID WILLIAMS |