Eplan. New 2-Story ADU Per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 8/5/2025
Issuing Office
Current Status
Issued on 8/5/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/1/2024 APPLICANT
Assigned to Plan Check Engineer 5/16/2024 GEORGE JOLAKIAN
Corrections Issued 5/21/2024 GEORGE JOLAKIAN
Quality Review Completed 5/30/2024 RODOLFO ARIAS
Plan Check Approved 7/17/2025 GEORGE JOLAKIAN
Issued 8/5/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/10/2024 JEANIE LAM
BHO/Hillside ordinance Cleared 7/10/2024 JEANIE LAM
BHO/Hillside ordinance Cleared 7/10/2024 JEANIE LAM
BHO/Hillside ordinance Cleared 7/10/2024 JEANIE LAM
BHO/Hillside ordinance Cleared 7/10/2024 JEANIE LAM
BHO/Hillside ordinance Cleared 7/10/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/18/2024 JEANIE LAM
Sewer availability Cleared 7/18/2024 JEANIE LAM
Construction near power lines Cleared 12/3/2024 TINA MIRANDA
Roof/Waste drainage to street Cleared 1/22/2025 JEANIE LAM
GPI Written Notices Cleared 7/17/2025 GEORGE JOLAKIAN
Grading Pre-Inspection Cleared 7/17/2025 GEORGE JOLAKIAN
Hold Cleared 5/12/2026 MARIA VENDIVIL

Contact Information

Contractor D & A Home Renovations; Lic. No.: 808672-B       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/8/2025 Partial Approval ANTHONY RAMOS
Excavation/Setback/Form/Re-Bar 8/21/2025 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 9/30/2025 No Access for Inspection FREDDIE RIVERA
METHANE-Barrier 9/30/2025 No Access for Inspection FREDDIE RIVERA
METHANE-Subgrade 9/30/2025 No Access for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 10/6/2025 Partial Approval FREDDIE RIVERA
METHANE-Barrier 10/6/2025 Partial Inspection FREDDIE RIVERA
METHANE-Subgrade 10/6/2025 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 10/27/2025 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 10/27/2025 Partial Inspection FREDDIE RIVERA
METHANE-Barrier 10/27/2025 Partial Inspection FREDDIE RIVERA
METHANE-Subgrade 10/27/2025 Partial Inspection FREDDIE RIVERA
Deputy Methane Barrier 10/31/2025 Conditional Approval REGINA MENDEZ
METHANE-Subgrade 10/31/2025 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 12/4/2025 Partial Inspection FREDDIE RIVERA
METHANE-Barrier 12/4/2025 Partial Inspection FREDDIE RIVERA
METHANE-Subgrade 12/4/2025 Corrections Issued FREDDIE RIVERA
Deputy Methane Barrier 12/5/2025 Conditional Approval OSVALDO PARAMO
Deputy Methane Barrier 12/8/2025 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 12/8/2025 Approved FREDDIE RIVERA
METHANE-Barrier 12/8/2025 Approved FREDDIE RIVERA
METHANE-Subgrade 12/8/2025 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 1/9/2026 Partial Approval FREDDIE RIVERA
Wood Frame 1/9/2026 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 1/13/2026 Partial Approval FREDDIE RIVERA
Wood Frame 1/13/2026 Partial Inspection FREDDIE RIVERA
Shower Pan 1/27/2026 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 2/4/2026 No Access for Inspection FREDDIE RIVERA
HVAC-Rough 2/4/2026 No Access for Inspection FREDDIE RIVERA
PLUMBING-Rough 2/4/2026 No Access for Inspection FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 2/4/2026 No Access for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 2/6/2026 Partial Inspection FREDDIE RIVERA
HVAC-Rough 2/6/2026 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 2/6/2026 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 2/17/2026 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/17/2026 Approved FREDDIE RIVERA
HVAC-Rough 2/17/2026 Approved FREDDIE RIVERA
PLUMBING-Rough 2/17/2026 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 2/19/2026 Not Ready for Inspection WILLIAM SIERRA
Green Building Rough 2/19/2026 Not Ready for Inspection WILLIAM SIERRA
METHANE-Rough 2/19/2026 Not Ready for Inspection WILLIAM SIERRA
Verify Sprinkler Sign Off 2/19/2026 Not Ready for Inspection WILLIAM SIERRA
Interior/Exterior Lathing 2/27/2026 Corrections Issued ALIZAH MAYAGOITIA
Deputy Methane Barrier 3/24/2026 Conditional Approval OSVALDO PARAMO
Wood Frame 3/27/2026 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 3/31/2026 Corrections Issued FREDDIE RIVERA
Green Building Rough 3/31/2026 Conditional Approval FREDDIE RIVERA
METHANE-Rough 3/31/2026 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 3/31/2026 Approved FREDDIE RIVERA
Wood Frame 3/31/2026 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 4/3/2026 No Access for Inspection FREDDIE RIVERA
Green Building Rough 4/3/2026 Corrections Issued FREDDIE RIVERA
Wood Frame 4/8/2026 Corrections Issued FREDDIE RIVERA
Insulation 4/23/2026 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 4/27/2026 Approved FREDDIE RIVERA
Green Building Rough 4/27/2026 Approved FREDDIE RIVERA
Drywall Nailing 5/1/2026 Approved FREDDIE RIVERA
Interior/Exterior Lathing 5/14/2026 Partial Approval FREDDIE RIVERA
Interior/Exterior Lathing 5/18/2026 Approved FREDDIE RIVERA
Interior/Exterior Lathing 5/19/2026 Approved GEM DE OCAMPO