2311 W HILL DR 90041

Certificate Information: 2311 W HILL DR 90041

Application / Permit
24010-10000-01790
Plan Check / Job No.
B24LA08009
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1) (1-STORY)
Permit Issued
Issued on 2/3/2025
Issuing Office
Current Status
CofO Issued on 10/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 CARLOS MONTES
Corrections Issued 5/16/2024 CARLOS MONTES
Quality Review Completed 5/22/2024 GARO TELMI
Applicant returned to address corrections 8/29/2024 CARLOS MONTES
Plan Check Approved 1/15/2025 CARLOS MONTES
Issued 2/3/2025 APPLICANT
CofO in Progress 10/1/2025 DAVID WILLIAMS
Permit Finaled 10/4/2025 DEROLD HAUFF
CofO Issued 10/4/2025 DEROLD HAUFF
Permit Finaled 10/4/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/3/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 7/3/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/5/2024 JEANIE LAM
Sewer availability Cleared 7/5/2024 JEANIE LAM
GPI Written Notices Cleared 8/29/2024 CARLOS MONTES
Grading Pre-Inspection Cleared 8/29/2024 RUSSELL BONVOULOIR
Hydrant and Access approval Cleared 9/10/2024 KURT CORRAL

Contact Information

Architect Yeo,, Ku Ho; Lic. No.: NA21041       ,
Contractor C S K Construction; Lic. No.: 1097998-B       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Reinforced Concrete Frame 3/25/2025 Approved DAVID WILLIAMS
Reinforced Concrete Frame 4/9/2025 Approved DAVID WILLIAMS
Reinforced Concrete Frame 4/24/2025 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 5/16/2025 Partial Approval DAVID WILLIAMS
Wood Frame 5/16/2025 Not Ready for Inspection DAVID WILLIAMS
BUILDING-Rough-Frame 5/30/2025 Approved DAVID WILLIAMS
ELECTRICAL-Rough 5/30/2025 Approved DAVID WILLIAMS
Green Building Rough 5/30/2025 Approved DAVID WILLIAMS
HVAC-Rough 5/30/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 5/30/2025 Approved DAVID WILLIAMS
Verify Sprinkler Sign Off 5/30/2025 Approved DAVID WILLIAMS
Insulation 6/6/2025 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 6/6/2025 Partial Approval BRIAN SULLIVAN
Shower Pan 6/6/2025 Approved BRIAN SULLIVAN
Drywall Nailing 6/11/2025 Approved REGINA MENDEZ
Sewer 7/9/2025 Approved LILIANA PORTILLO
Underground Mechanical 7/9/2025 Corrections Issued LILIANA PORTILLO
Sewer 7/24/2025 Partial Approval DAVID WILLIAMS
Underground Mechanical 7/24/2025 Approved DAVID WILLIAMS
Final 9/11/2025 Not Ready for Inspection DAVID WILLIAMS
Footing/Foundation/Slab 9/11/2025 Approved DAVID WILLIAMS
Green Building Final 9/11/2025 Corrections Issued DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 9/11/2025 SGSOV Approved DAVID WILLIAMS
Service/Power Release 9/11/2025 Not Ready for Inspection DAVID WILLIAMS
Smoke Detectors 9/11/2025 Approved DAVID WILLIAMS
Final 9/26/2025 Corrections Issued DAVID WILLIAMS
Grading Pre-Inspection 9/26/2025 Not Ready for Inspection DAVID WILLIAMS
Green Building Final 9/26/2025 Approved DAVID WILLIAMS
Service/Power Release 9/26/2025 Approved DAVID WILLIAMS
Final 10/1/2025 OK to Issue CofO DAVID WILLIAMS