3452 S ASHWOOD AVE 90066
Certificate Information: 3452 S ASHWOOD AVE 90066
- Application / Permit
- 24010-10000-01773
- Plan Check / Job No.
- B24LA07943
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 6/26/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2024 | DANIEL YIP |
| Corrections Issued | 5/6/2024 | DANIEL YIP |
| Quality Review Completed | 5/8/2024 | KEN GILL |
| Building Plans Picked Up | 5/13/2024 | APPLICANT |
| Applicant returned to address corrections | 6/11/2024 | DANIEL YIP |
| Plan Check Approved | 6/21/2024 | DANIEL YIP |
| Issued | 6/26/2024 | APPLICANT |
| CofO in Progress | 3/17/2025 | MICHAEL ALLEN |
| CofO Issued | 3/25/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/25/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 5/29/2024 | BRENDEN HAWK |
| Roof/Waste drainage to street | Cleared | 5/29/2024 | BRENDEN HAWK |
| Grading Pre-Inspection | Cleared | 5/30/2024 | LANNY MERRICK |
| Specific Plan | Cleared | 5/31/2024 | RICHARD WOO |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2024 | ANDREA SAINT-ANTONIN |
| Sewer availability | Cleared | 6/3/2024 | ANDREA SAINT-ANTONIN |
| Hydrant and Access approval | Cleared | 6/11/2024 | GILBERT URREA |
| GPI Written Notices | Cleared | 6/21/2024 | DANIEL YIP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/11/2024 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/19/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 9/25/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Partial Approval | JESUS PINEDA |
| Deputy Wood Construction | 9/26/2024 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 9/26/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 9/26/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 10/7/2024 | Approved | REGINA MENDEZ |
| Shower Pan | 10/7/2024 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 10/11/2024 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 10/11/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/15/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 10/15/2024 | Approved | JESUS PINEDA |
| Wood Frame | 10/15/2024 | Approved | JESUS PINEDA |
| Insulation | 10/31/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 11/6/2024 | Approved | REGINA MENDEZ |
| ELECTRICAL-Final | 2/20/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 2/21/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 2/26/2025 | Approved | MICHAEL ALLEN |
| Final | 3/12/2025 | Conditional Approval | MICHAEL ALLEN |
| Green Building Final | 3/12/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 3/12/2025 | SGSOV Approved | MICHAEL ALLEN |
| Service/Power Release | 3/12/2025 | Approved | MICHAEL ALLEN |
| Smoke Detectors | 3/12/2025 | Approved | MICHAEL ALLEN |
| Final | 3/14/2025 | OK to Issue CofO | MICHAEL ALLEN |