16780 W OTSEGO ST 91436
Certificate Information: 16780 W OTSEGO ST 91436
- Application / Permit
- 24010-10000-01750
- Plan Check / Job No.
- B24LA06949
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B)
- Permit Issued
- Issued on 9/7/2024
- Issuing Office
- Current Status
- Issued on 9/7/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2024 | CARLOS MONTES |
| Corrections Issued | 4/29/2024 | CARLOS MONTES |
| Quality Review Completed | 5/2/2024 | GARO TELMI |
| Plan Check Approved | 9/3/2024 | CARLOS MONTES |
| Issued | 9/7/2024 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 5/10/2024 | SARAH YOUSSEF |
| Address approval | Cleared | 6/4/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/4/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/5/2024 | BIAINA HARITUNIAN |
| Permit | Cleared | 6/17/2024 | BIAINA HARITUNIAN |
| Trees in Parkway | Cleared | 6/18/2024 | ADALBERTO VERA |
| Construction near power lines | Cleared | 8/14/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/20/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 11/20/2024 | Conditional Approval | THOMAS FINNILA |
| Underground Mechanical | 11/20/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 11/27/2024 | Conditional Approval | THOMAS FINNILA |
| Underground Mechanical | 11/27/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 12/5/2024 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Wood Construction | 1/16/2025 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 2/6/2025 | Corrections Issued | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 2/14/2025 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 2/14/2025 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/20/2025 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 2/20/2025 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 3/3/2025 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/10/2025 | Approved | THOMAS FINNILA |
| Green Building Rough | 3/10/2025 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 3/10/2025 | Approved | THOMAS FINNILA |
| Insulation | 3/25/2025 | Approved | MORRIS JACKSON |
| Drywall Nailing | 4/1/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 4/1/2025 | Corrections Issued | THOMAS FINNILA |
| Drywall Nailing | 4/7/2025 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 4/7/2025 | Partial Approval | MORRIS JACKSON |
| Shower Pan | 4/7/2025 | Not Ready for Inspection | MORRIS JACKSON |
| HVAC-Final | 11/17/2025 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 11/17/2025 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 12/4/2025 | Corrections Issued | THOMAS FINNILA |
| Final | 12/4/2025 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 12/4/2025 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 12/4/2025 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 3/5/2026 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 3/5/2026 | Not Ready for Inspection | THOMAS FINNILA |
| Service/Power Release | 4/1/2026 | Approved | THOMAS FINNILA |
| Final | 4/2/2026 | Partial Approval | THOMAS FINNILA |
| Green Building Final | 4/2/2026 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 4/2/2026 | Approved | THOMAS FINNILA |