4209 N ELMER AVE 91602

Certificate Information: 4209 N ELMER AVE 91602

Application / Permit
24010-10000-01664
Plan Check / Job No.
B24LA07488
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD W/ ATTACHED 2-CAR GARAGE, REAR COVER LOGGIA, FRONT DECK, MASTER BEDROOM DECK, AND ATTACHED TRUSS SYSTEM
Permit Issued
Issued on 10/2/2024
Issuing Office
Current Status
CofO Issued on 5/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2024 APPLICANT
Assigned to Plan Check Engineer 4/25/2024 KHEDER ALRAZAA
Corrections Issued 4/27/2024 KHEDER ALRAZAA
Quality Review Completed 5/3/2024 KEN GILL
Building Plans Picked Up 5/7/2024 APPLICANT
Applicant returned to address corrections 7/30/2024 KHEDER ALRAZAA
Plan Check Approved 9/24/2024 KHEDER ALRAZAA
Issued 10/2/2024 APPLICANT
CofO in Progress 5/4/2026 JAVIER RAMOS JR
Permit Finaled 5/8/2026 RUBEN SALAS
CofO Issued 5/8/2026 RUBEN SALAS
Permit Finaled 5/8/2026 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 5/30/2024 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 6/25/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/26/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/26/2024 BIAINA HARITUNIAN
ZI Cleared 8/9/2024 DORIAN AGUILAR
ZI Cleared 8/9/2024 DORIAN AGUILAR
Permit Cleared 9/6/2024 JOHN LIN
Trees in Parkway Cleared 9/10/2024 ADALBERTO VERA
Hydrant and Access approval Cleared 9/16/2024 LAVEON RIDER

Contact Information

Contractor Jd Emory, Inc; Lic. No.: 1126884-B 16133 VENTURA BOULEVARD   STE 700    ENCINO, CA 91436
Engineer Hanna,, Arsanious Michael; Lic. No.: C70743 13408 NAOMA LN      CERRITOS, CA 90703
Landscape Architect Crystal,, Jordan Todd; Lic. No.: LA5843 2815 PORTER LANE      VENTURA, CA 93003

Inspector Information

DANIEL ORRANTE, (818) 374-1157 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/10/2024 Partial Approval JENNIFER RABUCHIN
Sewer 10/10/2024 Approved JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 10/18/2024 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 10/18/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/4/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 12/4/2024 Partial Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 12/4/2024 Partial Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/25/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 2/25/2025 Partial Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 2/25/2025 Partial Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/7/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 3/7/2025 Partial Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 3/7/2025 Partial Inspection CHRISTOPHER ROJAS
Wood Frame 3/7/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 3/21/2025 Approved CHRISTOPHER ROJAS
Pre-Inspection 4/17/2025 Approved JAVIER RAMOS JR
HVAC-Rough 5/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Shower Pan 5/5/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Deputy Steel/Welding 5/30/2025 Conditional Approval JAVIER RAMOS JR
HVAC-Rough 6/4/2025 Partial Inspection JAVIER RAMOS JR
Underground Mechanical 6/4/2025 Partial Approval JAVIER RAMOS JR
Insulation 6/12/2025 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 6/12/2025 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 6/18/2025 Not Ready for Inspection JAVIER RAMOS JR
Green Building Rough 6/18/2025 Approved JAVIER RAMOS JR
Insulation 6/18/2025 Partial Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 6/18/2025 Partial Approval JAVIER RAMOS JR
Masonry Wall/Backfill 6/18/2025 Partial Approval JAVIER RAMOS JR
Verify Sprinkler Sign Off 6/18/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/23/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/1/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 7/1/2025 Approved JAVIER RAMOS JR
HVAC-Rough 7/1/2025 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 7/7/2025 Partial Inspection JAVIER RAMOS JR
Insulation 7/7/2025 Approved JAVIER RAMOS JR
Drywall Nailing 7/15/2025 Approved JAVIER RAMOS JR
HVAC-Rough 7/15/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/23/2025 Approved JUAN VALENZUELA
Underground Mechanical 12/30/2025 Partial Approval JUAN VALENZUELA
Masonry Wall/Backfill 1/8/2026 Not Ready for Inspection JOAQUIN GREENOUGH
Pre-Inspection 1/8/2026 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Final 5/4/2026 Approved JAVIER RAMOS JR
Final 5/4/2026 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 5/4/2026 Approved JAVIER RAMOS JR
HVAC-Final 5/4/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 5/4/2026 Approved JAVIER RAMOS JR
Service/Power Release 5/4/2026 Approved JAVIER RAMOS JR
Smoke Detectors 5/4/2026 Approved JAVIER RAMOS JR