Excavation/Setback/Form/Re-Bar
|
1/22/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
2/11/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
2/11/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Reinforced Concrete Frame
|
2/11/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
2/26/2025
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
2/26/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
3/6/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
3/6/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Reinforced Concrete Frame
|
3/6/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
3/25/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
4/8/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Pre-Inspection
|
4/9/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Deputy Steel/Welding
|
5/19/2025
|
Conditional Approval
|
RAFAEL CORTES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/19/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/20/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/22/2025
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/3/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wall Anchors
|
6/4/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wall Anchors
|
6/11/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wall Anchors
|
7/3/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Pre-Inspection
|
7/8/2025
|
Partial Approval
|
ALFREDO LOPEZ
|
|
Wall Anchors
|
7/8/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/11/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/24/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wall Anchors
|
7/24/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Deputy Steel/Welding
|
7/29/2025
|
Conditional Approval
|
RAFAEL CORTES
|
|
Insulation
|
7/29/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/5/2025
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/8/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Pre-Inspection
|
8/28/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Drywall Nailing
|
9/4/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Insulation
|
9/4/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/15/2025
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/17/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
9/19/2025
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Reinforced Concrete Frame
|
9/22/2025
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
10/1/2025
|
Conditional Approval
|
RAFAEL CORTES
|
|
Drywall Nailing
|
10/1/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
10/1/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Pre-Inspection
|
10/10/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Drywall Nailing
|
10/23/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/23/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Green Building Rough
|
10/23/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Verify Sprinkler Sign Off
|
10/23/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
10/23/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Deputy Drilled-In Anchors
|
10/27/2025
|
Conditional Approval
|
RAFAEL CORTES
|
|
Deputy Reinf. Concrete
|
10/27/2025
|
Conditional Approval
|
RAFAEL CORTES
|
|
Green Building Rough
|
10/27/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Verify Sprinkler Sign Off
|
10/27/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
10/27/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
10/28/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Reinforced Concrete Frame
|
10/28/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Green Building Rough
|
10/31/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Verify Sprinkler Sign Off
|
10/31/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
10/31/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Green Building Rough
|
11/6/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Verify Sprinkler Sign Off
|
11/6/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
11/6/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Drywall Nailing
|
11/13/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
11/24/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Drywall Nailing
|
12/9/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Pre-Inspection
|
1/14/2026
|
Partial Approval
|
JOEY BUCHANAN
|
|
Light Gage Steel Frame
|
2/4/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Light Gage Steel Frame
|
2/12/2026
|
Partial Approval
|
JOEY BUCHANAN
|
|
Pre-Inspection
|
2/19/2026
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Steel/Welding
|
2/23/2026
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Reinforced Concrete Frame
|
4/22/2026
|
Partial Approval
|
RAFAEL CORTES
|
|
Insulation
|
6/3/2026
|
Approved
|
JOEY BUCHANAN
|
|
Pre-Inspection
|
6/3/2026
|
Approved
|
JOEY BUCHANAN
|