2933 S SELBY AVE 90034

Certificate Information: 2933 S SELBY AVE 90034

Application / Permit
24010-10000-01605
Plan Check / Job No.
B24LA07190
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). ALL WORK PER ENG.
Permit Issued
Issued on 11/21/2024
Issuing Office
Current Status
CofO Issued on 10/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2024 APPLICANT
Assigned to Plan Check Engineer 4/26/2024 LUISANGEL VALENZUELA
Corrections Issued 4/27/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 9/10/2024 LUISANGEL VALENZUELA
Plan Check Approved 9/16/2024 SARKIS HARABEDIAN
Issued 11/21/2024 APPLICANT
CofO in Progress 10/13/2025 KIRK SANDERS
Permit Finaled 10/21/2025 RICHARD STEINBACH
CofO Issued 10/21/2025 RICHARD STEINBACH
Permit Finaled 10/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/2/2024 VLADIMIR ARUTYUNYAN
Specific Plan Cleared 5/2/2024 JULISSA LOPEZ-HODOYAN
ZI Cleared 5/2/2024 JULISSA LOPEZ-HODOYAN
Specific Plan Cleared 5/6/2024 MOHAMMAD HASAN
Specific Plan Cleared 5/6/2024 MOHAMMAD HASAN
Grading Pre-Inspection Cleared 5/10/2024 VASIL MIHALEV
Eng Process Fee Ord 176,300 Cleared 6/5/2024 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 6/5/2024 VLADIMIR ARUTYUNYAN
Construction near power lines Cleared 8/26/2024 RIDWAN HARDY
Roof/Waste drainage to street Cleared 9/7/2024 LIAM ODONOVAN
GPI Written Notices Cleared 9/16/2024 LUISANGEL VALENZUELA
Hold Cleared 3/25/2025 MARIA VENDIVIL

Contact Information

Contractor Aligcus Construction Llc; Lic. No.: 1105980-B       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/27/2025 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 4/3/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 4/22/2025 No Access for Inspection TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 4/28/2025 Approved WILBER ROSALES
Rough-Elec/Plmb/HVAC 4/28/2025 Corrections Issued WILBER ROSALES
ELECTRICAL-Rough 5/23/2025 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Partial Approval EVAN COOPER
HVAC-Rough 5/23/2025 Approved EVAN COOPER
PLUMBING-Rough 5/23/2025 Approved EVAN COOPER
Underground Mechanical 5/23/2025 Partial Approval EVAN COOPER
Insulation 6/9/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 6/9/2025 Approved CARLOS MATAMOROS
Shower Pan 6/9/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 6/10/2025 Approved EVAN COOPER
MERV13>=Rough 6/10/2025 Approved EVAN COOPER
Drywall Nailing 7/3/2025 Approved ASHLEY THOMPSON
Sewer 7/10/2025 Approved EVAN COOPER
Underground Mechanical 7/10/2025 Partial Approval EVAN COOPER
ELECTRICAL-Final 9/12/2025 Approved JESUS RODRIGUEZ
Final 9/12/2025 Conditional Approval JESUS RODRIGUEZ
HVAC-Final 9/12/2025 Approved JESUS RODRIGUEZ
MERV13>=Final 9/12/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 9/12/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Not Required JESUS RODRIGUEZ
Smoke Detectors 9/12/2025 Approved JESUS RODRIGUEZ
Final 10/10/2025 OK to Issue CofO KIRK SANDERS