11955 W MODJESKA PL 90066
Certificate Information: 11955 W MODJESKA PL 90066
- Application / Permit
- 24010-10000-01598
- Plan Check / Job No.
- B24LA07155
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: (N) 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 10/17/2024
- Issuing Office
- Current Status
- CofO Issued on 5/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2024 | DANIEL YIP |
| Corrections Issued | 4/27/2024 | DANIEL YIP |
| Quality Review Completed | 5/14/2024 | GARO TELMI |
| Applicant returned to address corrections | 8/12/2024 | DANIEL YIP |
| Applicant returned to address corrections | 9/6/2024 | DANIEL YIP |
| Plan Check Approved | 9/19/2024 | DANIEL YIP |
| Plan Check Approved | 10/10/2024 | DANIEL YIP |
| No Progress | 10/11/2024 | DANIEL YIP |
| Plan Check Approved | 10/11/2024 | DANIEL YIP |
| Issued | 10/17/2024 | APPLICANT |
| CofO in Progress | 5/18/2026 | BOBBY KEY |
| Permit Finaled | 5/19/2026 | RICHARD STEINBACH |
| CofO Issued | 5/19/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/19/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 5/24/2024 | SARAH YOUSSEF |
| Address approval | Cleared | 5/31/2024 | BRENDEN HAWK |
| Eng Process Fee Ord 176,300 | Cleared | 5/31/2024 | BRENDEN HAWK |
| Permit | Cleared | 5/31/2024 | BRENDEN HAWK |
| Roof/Waste drainage to street | Cleared | 5/31/2024 | BRENDEN HAWK |
| Sewer availability | Cleared | 5/31/2024 | BRENDEN HAWK |
| Trees in Parkway | Cleared | 6/14/2024 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 7/6/2024 | RUEL COLE |
| GPI Written Notices | Cleared | 8/12/2024 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 8/12/2024 | DANIEL YIP |
| SB8 RUD | Cleared | 10/7/2024 | SHARON WILLIAMS |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: NA23971 | , |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | , |
| Engineer | Nguyen,, Huan; Lic. No.: NA64238 | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/30/2024 | No Access for Inspection | JESUS RODRIGUEZ |
| Underground Mechanical | 1/2/2025 | Partial Approval | DANIEL VERA |
| Sewer | 1/3/2025 | Approved | DANIEL VERA |
| Sewer | 1/8/2025 | Approved | DANIEL VERA |
| Underground Mechanical | 1/8/2025 | Partial Approval | DANIEL VERA |
| Footing/Foundation/Slab | 1/15/2025 | Approved | DANIEL VERA |
| Deputy Reinf. Concrete | 1/17/2025 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2025 | Approved | DANIEL VERA |
| Wood Frame | 2/27/2025 | Approved | DANIEL VERA |
| HVAC-Rough | 3/12/2025 | Corrections Issued | WILBER ROSALES |
| ELECTRICAL-Rough | 3/18/2025 | Approved | WILBER ROSALES |
| HVAC-Rough | 3/18/2025 | Corrections Issued | WILBER ROSALES |
| PLUMBING-Rough | 3/18/2025 | Corrections Issued | WILBER ROSALES |
| Special/Order Compliance | 3/18/2025 | Partial Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/21/2025 | Approved | WILBER ROSALES |
| Special/Order Compliance | 3/21/2025 | Partial Inspection | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 3/27/2025 | Corrections Issued | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2025 | Approved | WILBER ROSALES |
| Green Building Rough | 3/27/2025 | Not Ready for Inspection | WILBER ROSALES |
| Verify Sprinkler Sign Off | 3/27/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 4/7/2025 | Approved | BOBBY KEY |
| Green Building Rough | 4/7/2025 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/7/2025 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 4/7/2025 | Approved | BOBBY KEY |
| Insulation | 4/14/2025 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 4/16/2025 | Partial Approval | WILBER ROSALES |
| Drywall Nailing | 4/22/2025 | Approved | WILBER ROSALES |
| Shower Pan | 5/1/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 9/24/2025 | Approved | EVAN COOPER |
| HVAC-Final | 9/24/2025 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Final | 9/24/2025 | Approved | EVAN COOPER |
| Service/Power Release | 9/24/2025 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 9/24/2025 | Approved | EVAN COOPER |
| Service/Power Release | 9/30/2025 | Approved | MICHAEL PELHAM |
| HVAC-Final | 3/2/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Final | 3/2/2026 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 3/23/2026 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 4/7/2026 | Approved | EVAN COOPER |
| Final | 4/14/2026 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 4/14/2026 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 4/14/2026 | SGSOV Not Required | JESUS PINEDA |
| Final | 4/21/2026 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 4/27/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 5/15/2026 | OK to Issue CofO | BOBBY KEY |