10917-10919 W MASSACHUSETTS AVE 90024

Certificate Information: 10917-10919 W MASSACHUSETTS AVE 90024

Application / Permit
24010-10000-01575
Plan Check / Job No.
B24LA07043
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
[ePlan] New 2-Story Duplex with attached 2-Car Garage per SB9 (Two Unit Development) - Bldg Sprinklered Thru-out
Permit Issued
Issued on 4/17/2025
Issuing Office
Current Status
Issued on 4/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/17/2024 APPLICANT
Assigned to Plan Check Engineer 5/2/2024 MAHNAZ NOURHASHEMI
Corrections Issued 5/7/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 5/23/2024 TU HUA
Applicant returned to address corrections 12/12/2024 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 1/29/2025 MAHNAZ NOURHASHEMI
Plan Check Approved 2/24/2025 MAHNAZ NOURHASHEMI
Issued 4/17/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/13/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 5/13/2024 DARIN LAM
Sewer availability Cleared 5/13/2024 DARIN LAM
Low Impact Development (LID) Cleared 5/14/2024 LUIS LUVANO
Hydrant and Access approval Cleared 6/16/2024 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 7/18/2024 DARIN LAM
Specific Plan Cleared 9/18/2024 RICHARD WOO
GPI Written Notices Cleared 10/21/2024 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 10/21/2024 MAHNAZ NOURHASHEMI
Senate Bill 9 Cleared 11/1/2024 MATHEW QUAN
ZA Case Cleared 11/1/2024 MATHEW QUAN
Miscellaneous Cleared 2/20/2025 DIANA RENTERIA

Contact Information

Architect Stockton,, Richard Kenneth; Lic. No.: NA35492       ,
Contractor Elm Construction; Lic. No.: 1099704-B       ,
Contractor Elm Group La Inc; Lic. No.: 1099704-B       ,
Engineer Van, Elden, Alexander; Lic. No.: C71696 2415 FORDHAM DR      COSTA MESA, CA 92626

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/27/2025 Corrections Issued KIRK SANDERS
Gas Test 8/6/2025 Corrections Issued SEAN HAUPT
Sewer 8/6/2025 Partial Approval SEAN HAUPT
Underground Mechanical 8/6/2025 Partial Approval SEAN HAUPT
PLUMBING-Rough 8/15/2025 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 8/22/2025 Partial Approval ARAM AVEDISIAN
Sewer 8/22/2025 Approved ARAM AVEDISIAN
Footing/Foundation/Slab 9/15/2025 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 9/30/2025 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/31/2025 Partial Approval MICHAEL ALLEN
Wood Frame 10/31/2025 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 12/3/2025 Partial Approval EVAN COOPER
ELECTRICAL-Rough 12/9/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 12/9/2025 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 12/9/2025 Not Ready for Inspection MICHAEL ALLEN
Interior/Exterior Lathing 1/14/2026 Approved MICHAEL ALLEN
Gas Test 1/23/2026 Conditional Approval MICHAEL ALLEN
Rough-Elec/Plmb/HVAC 1/23/2026 Approved MICHAEL ALLEN
Shower Pan 1/23/2026 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 2/2/2026 Corrections Issued MICHAEL ALLEN
Green Building Rough 2/2/2026 Approved MICHAEL ALLEN
Verify Sprinkler Sign Off 2/2/2026 Not Ready for Inspection MICHAEL ALLEN
Insulation 2/26/2026 Corrections Issued WILBER ROSALES
Insulation 3/4/2026 Approved RYAN SALAZAR
Drywall Nailing 3/6/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 3/17/2026 Approved MICHAEL ALLEN
Underground Mechanical 6/5/2026 Partial Approval WILBER ROSALES
Underground Mechanical 6/8/2026 Corrections Issued ANTHONY EGSON